Site Accessibility Information Access Key 1 to Skip to Top Navigation Access Key 2 to Skip to the Three One One link Access Key 3 to Skip to City of Winnipeg Main Menu Access Key 4 to Skip to Left Navigation Menu Access Key 5 to Skip to Content area Access Key 6 to Skip to Right Sidebar content area Access Key 7 to Skip to Footer Links
City of Winnipeg
|  Link to the City of Winnipeg French websiteFrançais  |

Public Works

Road Construction List

The roadway construction list provides 2017 project information in alphabetical order by street name. Project information is available by location in both map and list format. Please see the regional street lane closures page for information on current lane closures on major streets.

How to use the construction list

Click on the + beside the project name. A dropdown box will appear with these project details:

  1. type of infrastructure (street, alley, sidewalk, traffic signal, bridge project, pedestrian and cycling path),
  2. type of construction work (reconstruction, rehabilitation, mill & fill, thin bituminous overlay, improvements within the right-of-way)
  3. estimated to start,
  4. estimated to end,
  5. approximate percentage completed:
    • Pre-Construction – Construction phase has not started.
    • 0% – Construction contract is in place, but crews have not mobilized to the site.
    • 5% – Crews have mobilized to the site and construction has just begun.
    • 10% 90% – An approximation of progress; construction is well underway.
    • 95% – Main roadway construction is complete; travelling lanes are open/parking is restored/garbage pickup resumes (depending on the location); minor deficiencies and landscaping (seeding/sod) are likely outstanding.
    • COMPLETE – All construction components of the project are complete. Contractor may return for any follow up or warranty work in the next 1-2 years. Utilities (e.g. street lights) may or may not be complete. Construction may not be complete for other locations in the same contract.
  6. consultant information, and
  7. contractor information.

You can also view projects by street name using the Search box provided. Click "View Map" beside any project name to view in a map.

Note: As construction projects get underway this season the information about start dates and completion dates will be updated to reflect the actual project timeline.

City of Winnipeg - Public Works Capital Projects
(Last updated on November 17, 2017 @ 8:00 PM)
 
 
View All on Map


#171 McDermot Av   View Map
Facility type Sidewalk
Type of work Reconstruction
Estimated to start Mid July 2017
Estimated to end Mid September 2017
Approx. % completed Complete
Consultant City Of Winnipeg - Engineering Division
Contractor J.C. Paving Ltd.
Agnes St/Victor St - Ellice Av/Sargent Av   View Map
Facility type Alley
Type of work Reconstruction
Estimated to start Early May 2017
Estimated to end Early June 2017
Approx. % completed Complete
Consultant WSP Canada Inc.
Contractor J.C. Paving Ltd.
Aikins St - McAdam Av/Carruthers Av   View Map
Facility type Street
Type of work Reconstruction
Estimated to start Late June 2017
Estimated to end Mid October 2017
Approx. % completed Complete
Consultant MMM Group Limited
Contractor Darco Enterprises Ltd.
Aikins St - Mountain Av/Redwood Av   View Map
Facility type Street
Type of work Reconstruction
Estimated to start Early July 2017
Estimated to end Mid October 2017
Approx. % completed Complete
Consultant MMM Group Limited
Contractor Darco Enterprises Ltd.
Aikins St and Mountain Av Intersection   View Map
Facility type Signal
Type of work New - Pedestrian Corridor Installation
Estimated to start Early June 2017
Estimated to end Late October 2017
Approx. % completed Complete
Consultant City of Winnipeg - Transportation Division
Contractor Black & McDonald Limited
Alburg Dr - Paddington Rd/Longford Av   View Map
Facility type Street
Type of work TBO
Estimated to start Mid May 2017
Estimated to end Late May 2017
Approx. % completed Complete
Consultant KGS Group Limited
Contractor Nelson River Construction Inc.
Alexander Av - Yeomans St/McPhillips St   View Map
Facility type Street
Type of work Reconstruction
Estimated to start Late May 2017
Estimated to end Mid July 2017
Approx. % completed Complete
Consultant City Of Winnipeg - Engineering Division
Contractor Bayview Construction Ltd
Alsip Dr - Tallman St/Lucas Av   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Early July 2017
Estimated to end Mid October 2017
Approx. % completed Complete
Consultant MMM Group Limited
Contractor Bituminex Paving Ltd
Amelia Cr - McCreedy Rd/Tu Pelo Av   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Mid July 2017
Estimated to end Mid October 2017
Approx. % completed Complete
Consultant MMM Group Limited
Contractor Bayview Construction Ltd
Andrews St - Selkirk Av/Dufferin Av   View Map
Facility type Street
Type of work Reconstruction
Estimated to start Late June 2017
Estimated to end Late August 2017
Approx. % completed Complete
Consultant MMM Group Limited
Contractor Bituminex Paving Ltd
Anneville Cr - Ashmore Dr /Mandalay Dr   View Map
Facility type Street
Type of work TBO
Estimated to start Late July 2017
Estimated to end Mid August 2017
Approx. % completed Complete
Consultant City Of Winnipeg - Streets Maintenance Division
Contractor City Of Winnipeg - Centralized Services
Apple Ln - Quail Ridge Rd/Hamilton Av   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Early July 2017
Estimated to end Mid October 2017
Approx. % completed Complete
Consultant AECOM Canada Ltd
Contractor J.C. Paving Ltd.
Archibald St - Watt St/#80 Archibald St   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Early April 2017
Estimated to end Mid October 2017
Approx. % completed Complete
Consultant Stantec
Contractor M. D. Steele
Arlington St/Alverstone St - Notre Dame Av/Adele Av   View Map
Facility type Alley
Type of work Reconstruction
Estimated to start Early July 2017
Estimated to end Mid October 2017
Approx. % completed Complete
Consultant WSP Canada Inc.
Contractor J.C. Paving Ltd.
Armstrong Av - Scotia/Marymound Wy   View Map
Facility type Street
Type of work TBO
Estimated to start Mid June 2017
Estimated to end Late June 2017
Approx. % completed Complete
Consultant City Of Winnipeg - Streets Maintenance Division
Contractor City Of Winnipeg - Centralized Services
Attache Dr - Diplomat Dr/Ambassador Rw   View Map
Facility type Street
Type of work TBO
Estimated to start Late May 2017
Estimated to end Mid June 2017
Approx. % completed Complete
Consultant KGS Group Limited
Contractor Asphaltec Paving Ltd.
Aulneau St - Hamel Av/Dollard Bv   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Early August 2017
Estimated to end Early September 2017
Approx. % completed Complete
Consultant AECOM Canada Ltd
Contractor J.C. Paving Ltd.
Autumnwood Dr - Drake Bv/Echo By   View Map
Facility type Sidewalk
Type of work Reconstruction
Estimated to start Early July 2017
Estimated to end Late August 2017
Approx. % completed Complete
Consultant City Of Winnipeg - Engineering Division
Contractor Wintec Building Services Inc.
Banning St/Lipton St - Notre Dame Av/Yarwood Av   View Map
Facility type Alley
Type of work Reconstruction
Estimated to start Early July 2017
Estimated to end Spring 2018
Approx. % completed 80
Consultant WSP Canada Inc.
Contractor J.C. Paving Ltd.
Beghin Av - Dugald Rd/De Baets St   View Map
Facility type Street
Type of work Reconstruction
Estimated to start Late August 2017
Estimated to end Early Spring 2018
Approx. % completed Complete
Consultant KGS Group Limited
Contractor Bituminex Paving Ltd
Beresford Av - Daly St S/Cockburn St S   View Map
Facility type Street
Type of work TBO
Estimated to start Early July 2017
Estimated to end Mid July 2017
Approx. % completed Complete
Consultant City Of Winnipeg - Streets Maintenance Division
Contractor City Of Winnipeg - Centralized Services
Bishop Grandin Bv - Rapid Transit Corridor Overpass   View Map
Facility type Rapid Transit Corridor
Type of work Rapid Transit - New Overpass Installation
Estimated to start Early February 2017
Estimated to end Late September 2018
Approx. % completed 10
Consultant Plenary Roads
Contractor PCL
Additional information Click here
Bison Dr - Markham Rd/Waverley St   View Map
Facility type Street
Type of work Mill and Fill
Estimated to start Mid August 2017
Estimated to end Late August 2017
Approx. % completed Complete
Consultant City Of Winnipeg - Streets Maintenance Division
Contractor City Of Winnipeg - Centralized Services
Bournais Dr - Railway Crossing/Dugald Rd   View Map
Facility type Street
Type of work Reconstruction
Estimated to start Late August 2017
Estimated to end Early November 2017
Approx. % completed Complete
Consultant KGS Group Limited
Contractor Bituminex Paving Ltd
Boyd Av - Mcphillips St/Fife St   View Map
Facility type Street
Type of work TBO
Estimated to start Late May 2017
Estimated to end Late June 2017
Approx. % completed Complete
Consultant City Of Winnipeg - Streets Maintenance Division
Contractor City Of Winnipeg - Centralized Services
Brixford Cr - Bramton St/Ashworth St   View Map
Facility type Street
Type of work TBO
Estimated to start Mid May 2017
Estimated to end Late May 2017
Approx. % completed Complete
Consultant KGS Group Limited
Contractor Nelson River Construction Inc.
Broadway - Sherbrook St/Portage Av   View Map
Facility type Street
Type of work Mill and Fill
Estimated to start Early September 2017
Estimated to end Late September 2017
Approx. % completed Complete
Consultant Stantec
Contractor Bituminex Paving Ltd
Brookside Bv - 100m N of Inkster Bv/Mollard Rd   View Map
Facility type Street
Type of work Mill and Fill
Estimated to start Early August 2017
Estimated to end Late September 2017
Approx. % completed Complete
Consultant Stantec
Contractor Maple Leaf Construction Ltd.
Bruce Av - Linwood St/Winchester St   View Map
Facility type Sidewalk
Type of work Reconstruction
Estimated to start Early August 2017
Estimated to end Late August 2017
Approx. % completed Complete
Consultant City Of Winnipeg - Engineering Division
Contractor Wintec Building Services Inc.
Bryce St - Roslyn Rd/River Av   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Mid September 2017
Estimated to end Late October 2017
Approx. % completed Complete
Consultant MMM Group Limited
Contractor Bayview Construction Ltd
Burlington Wy - Columbia Dr/Columbia Dr   View Map
Facility type Street
Type of work TBO
Estimated to start Mid May 2017
Estimated to end Late May 2017
Approx. % completed Complete
Consultant KGS Group Limited
Contractor Asphaltec Paving Ltd.
Byng Pl - Riverside Dr/Pembina Hw   View Map
Facility type Street
Type of work Reconstruction
Estimated to start Late August 2017
Estimated to end Early October 2017
Approx. % completed Complete
Consultant MMM Group Limited
Contractor Bayview Construction Ltd
Cairnsmore St - Cathedral Av/Machray Av   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Late August 2016
Estimated to end Late May 2017
Approx. % completed Complete
Consultant AECOM Canada Ltd
Contractor Darco Enterprises Ltd.
Carlton St - York Av/Broadway   View Map
Facility type Sidewalk
Type of work Reconstruction
Estimated to start Mid July 2017
Estimated to end Mid September 2017
Approx. % completed Complete
Consultant City Of Winnipeg - Engineering Division
Contractor J.C. Paving Ltd.
Carpathia Rd - Willow Av/Tuxedo Av   View Map
Facility type Street
Type of work TBO
Estimated to start Late May 2017
Estimated to end Mid June 2017
Approx. % completed Complete
Consultant City Of Winnipeg - Streets Maintenance Division
Contractor City Of Winnipeg - Centralized Services
Chelsea Av - Brazier St/Henderson Hw   View Map
Facility type Street
Type of work TBO
Estimated to start Late May 2017
Estimated to end Early June 2017
Approx. % completed Complete
Consultant City Of Winnipeg - Streets Maintenance Division
Contractor City Of Winnipeg - Centralized Services
Chornick Dr - McIvor Av/Gilmore Av   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Early June 2017
Estimated to end Mid October 2017
Approx. % completed Complete
Consultant MMM Group Limited
Contractor Bayview Construction Ltd
Chrislind St - Ravelston Av W/Regent Av W   View Map
Facility type Street
Type of work Reconstruction
Estimated to start Early June 2017
Estimated to end Mid October 2017
Approx. % completed Complete
Consultant MMM Group Limited
Contractor Bayview Construction Ltd
Concordia Av - Louelda St/Moncton Av   View Map
Facility type Sidewalk
Type of work Reconstruction
Estimated to start Mid June 2017
Estimated to end Mid July 2017
Approx. % completed Complete
Consultant City Of Winnipeg - Engineering Division
Contractor J.C. Paving Ltd.
Crystal Av - St Annes Rd/St Thomas Rd   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Late August 2017
Estimated to end Late September 2017
Approx. % completed Complete
Consultant AECOM Canada Ltd
Contractor J.C. Paving Ltd.
Dale Bv - Rannock Av/955 Dale Bv   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Mid May 2017
Estimated to end Late June 2017
Approx. % completed Complete
Consultant AECOM Canada Ltd
Contractor Maple Leaf Construction Ltd.
Dawnville Dr - Devonshire Dr W/Kildonan Meadow Dr   View Map
Facility type Street
Type of work TBO
Estimated to start Mid July 2017
Estimated to end Early August 2017
Approx. % completed Complete
Consultant City Of Winnipeg - Streets Maintenance Division
Contractor City Of Winnipeg - Centralized Services
De Baets St - Paquin Rd/Beghin Av   View Map
Facility type Street
Type of work Reconstruction
Estimated to start Early August 2017
Estimated to end Early November 2017
Approx. % completed Complete
Consultant KGS Group Limited
Contractor Bituminex Paving Ltd
Deer Lodge Pl - Portage Av/Portage Av   View Map
Facility type Street
Type of work Reconstruction
Estimated to start Early July 2017
Estimated to end Late October 2017
Approx. % completed Complete
Consultant AECOM Canada Ltd
Contractor J.C. Paving Ltd.
Dells Cr- Hazelwood Av/Hazelwood Av   View Map
Facility type Street
Type of work TBO
Estimated to start Mid May 2017
Estimated to end Late May 2017
Approx. % completed Complete
Consultant KGS Group Limited
Contractor Nelson River Construction Inc.
Deniset St - Archibald St/Evans St   View Map
Facility type Street
Type of work TBO
Estimated to start Early June 2017
Estimated to end Mid June 2017
Approx. % completed Complete
Consultant KGS Group Limited
Contractor Nelson River Construction Inc.
Des Meurons St - Vivian Av/Regal Av   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Late July 2017
Estimated to end Early September 2017
Approx. % completed 90
Consultant AECOM Canada Ltd
Contractor J.C. Paving Ltd.
Dickens Dr - Bedson St/Bedson St   View Map
Facility type Street
Type of work TBO
Estimated to start Late May 2017
Estimated to end Early June 2017
Approx. % completed Complete
Consultant KGS Group Limited
Contractor Asphaltec Paving Ltd.
Donald St - Portage Av/Notre Dame Av   View Map
Facility type Street
Type of work Reconstruction
Estimated to start Late August 2017
Estimated to end Late October 2017
Approx. % completed 40
Consultant AECOM Canada Ltd
Additional information Click here
Donald St and Hargrave Pl Intersection   View Map
Facility type Signal
Type of work New - Pedestrian Corridor Installation
Estimated to start Early June 2017
Estimated to end Late October 2017
Approx. % completed Complete
Consultant City of Winnipeg - Transportation Division
Contractor Black & McDonald Limited
Donald St Bridge / Midtown Bridge   View Map
Facility type Bridge
Type of work Bridge Maintenance
Estimated to start Late May 2017
Estimated to end Late June 2017
Approx. % completed Complete
Consultant Dillon Consulting Limited
Contractor Gateway Construction & Engineering Ltd.
Dorchester Av/McMillan Av - Arbuthnot St/Lilac St   View Map
Facility type Alley
Type of work Reconstruction
Estimated to start Late August 2017
Estimated to end Mid October 2017
Approx. % completed Complete
Consultant WSP Canada Inc.
Contractor Bituminex Paving Ltd
Downing St - Wellington Av/Sargent Park Pl   View Map
Facility type Street
Type of work Reconstruction
Estimated to start Early July 2017
Estimated to end Mid August 2017
Approx. % completed Complete
Consultant City Of Winnipeg - Engineering Division
Contractor Bayview Construction Ltd
Dublin Av - Notre Dame Av/Orange St   View Map
Facility type Street
Type of work Mill and Fill
Estimated to start Early August 2017
Estimated to end Mid August 2017
Approx. % completed Complete
Consultant City Of Winnipeg - Streets Maintenance Division
Contractor City Of Winnipeg - Centralized Services
Dumoulin St - St Jean Baptiste St/Langevin St   View Map
Facility type Alley
Type of work Reconstruction
Estimated to start Late August 2017
Estimated to end Mid October 2017
Approx. % completed Complete
Consultant WSP Canada Inc.
Contractor Asphaltec Paving Ltd.
Dupont St - Dubuc St/Yardley St   View Map
Facility type Street
Type of work TBO
Estimated to start ON HOLD
Estimated to end ON HOLD
Approx. % completed Complete
Consultant City Of Winnipeg - Streets Maintenance Division
Contractor City Of Winnipeg - Centralized Services
Eaglemount Cr - Foxmeadow Dr/Foxmeadow Dr   View Map
Facility type Street
Type of work TBO
Estimated to start Early May 2017
Estimated to end Early June 2017
Approx. % completed Complete
Consultant KGS Group Limited
Contractor Asphaltec Paving Ltd.
Eastway - Empress St E/Empress St   View Map
Facility type Street
Type of work Mill and Fill
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Pre-Construction
Consultant Morrison Hershfield Limited
Additional information Click here
Edmonton St - From the Alley/Broadway   View Map
Facility type Sidewalk
Type of work Reconstruction
Estimated to start Early June 2017
Estimated to end Late July 2017
Approx. % completed Complete
Consultant City Of Winnipeg - Engineering Division
Contractor J.C. Paving Ltd.
Edmonton St - York Av/Broadway   View Map
Facility type Sidewalk
Type of work Reconstruction
Estimated to start Early June 2017
Estimated to end Late July 2017
Approx. % completed Complete
Consultant City Of Winnipeg - Engineering Division
Contractor J.C. Paving Ltd.
Ellice Av - Arlington St/Dominion St   View Map
Facility type Street
Type of work Reconstruction
Estimated to start Early August 2017
Estimated to end Mid October 2017
Approx. % completed 50
Consultant Stantec
Contractor Darco Enterprises Ltd.
Ellice Av - Dominion St/Erin St   View Map
Facility type Street
Type of work Reconstruction
Estimated to start Early August 2017
Estimated to end Early November 2017
Approx. % completed 60
Consultant Stantec
Contractor Darco Enterprises Ltd.
Empress St - Jack Blick Av/Portage Av   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Pre-Construction
Consultant Morrison Hershfield Limited
Additional information Click here
Empress St - Wellington Av/St Matthews Av   View Map
Facility type Street
Type of work Mill and Fill
Estimated to start Mid September 2017
Estimated to end Mid October 2017
Approx. % completed 80
Consultant City Of Winnipeg - Streets Maintenance Division
Contractor City Of Winnipeg - Centralized Services
Empress St E - Portage Av/Westway   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Pre-Construction
Consultant Morrison Hershfield Limited
Additional information Click here
Envoy Pl - End/Ambassador Rw   View Map
Facility type Street
Type of work TBO
Estimated to start Late May 2017
Estimated to end Mid June 2017
Approx. % completed Complete
Consultant KGS Group Limited
Contractor Asphaltec Paving Ltd.
Erin St/Clifton St - Ellice Av/St Matthews Av   View Map
Facility type Alley
Type of work Reconstruction
Estimated to start Early July 2017
Estimated to end Spring 2018
Approx. % completed 90
Consultant WSP Canada Inc.
Contractor J.C. Paving Ltd.
Eugenie St - Youville St/Des Meurons St   View Map
Facility type Sidewalk
Type of work Reconstruction
Estimated to start Early July 2017
Estimated to end Mid August 2017
Approx. % completed Complete
Consultant City Of Winnipeg - Engineering Division
Contractor Wintec Building Services Inc.
Fermor Av at Seine River Crossing   View Map
Facility type Bridge
Type of work Fermor Box Culvert & Roadworks
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Pre-Construction
Consultant Dillon Consulting Limited
Additional information Click here
Ferndale Av/Lawndale Av - Kirkdale St/Highfield St   View Map
Facility type Alley
Type of work Reconstruction
Estimated to start Mid July 2017
Estimated to end Mid October 2017
Approx. % completed Complete
Consultant WSP Canada Inc.
Contractor Asphaltec Paving Ltd.
Fernwood Av - St Andrew Rd/St David Rd   View Map
Facility type Sidewalk
Type of work Reconstruction
Estimated to start Late July 2017
Estimated to end Late August 2017
Approx. % completed Complete
Consultant City Of Winnipeg - Engineering Division
Contractor Darco Enterprises Ltd.
Garry St - Broadway/York Av   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Garry St - Notre Dame Av/Assiniboine   View Map
Facility type Street
Type of work Reconstruction
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Pre-Construction
Consultant AECOM Canada Ltd
Graham Av - Fort St/Vaughan   View Map
Facility type Street
Type of work Mill and Fill
Estimated to start Early August 2017
Estimated to end Late September 2017
Approx. % completed Complete
Consultant Stantec
Grant Ave - Campbell St/Borebank St   View Map
Facility type Street
Type of work Mill and Fill
Estimated to start Mid September 2017
Estimated to end Late September 2017
Approx. % completed Complete
Consultant City Of Winnipeg - Streets Maintenance Division
Contractor City Of Winnipeg - Centralized Services
Greendell Av - St Marys Rd/Minnetonka St   View Map
Facility type Sidewalk
Type of work Reconstruction
Estimated to start Late July 2017
Estimated to end Mid August 2017
Approx. % completed Complete
Consultant City Of Winnipeg - Engineering Division
Contractor Darco Enterprises Ltd.
Grosvenor Av - Cambridge St/Montrose St   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Early August 2016
Estimated to end Late May 2017
Approx. % completed Complete
Consultant MMM Group Limited
Contractor Bituminex Paving Ltd
Hartford Av - McGregor St/CPR WINNIPEG BEACH (Railway)   View Map
Facility type Street
Type of work Reconstruction
Estimated to start Early July 2017
Estimated to end Mid October 2017
Approx. % completed Complete
Consultant MMM Group Limited
Contractor Darco Enterprises Ltd.
Havelock Av/Portland Av - St Andrew Rd/St George Rd   View Map
Facility type Alley
Type of work Reconstruction
Estimated to start Late August 2017
Estimated to end Late October 2017
Approx. % completed Complete
Consultant WSP Canada Inc.
Contractor Asphaltec Paving Ltd.
Hazelwood Cr - Wyoming St/Iowa St   View Map
Facility type Sidewalk
Type of work New - Sidewalk Installation
Estimated to start Mid July 2017
Estimated to end Late July 2017
Approx. % completed Complete
Consultant City Of Winnipeg - Engineering Division
Contractor Darco Enterprises Ltd.
Hector Av - Stafford St/Wilton St   View Map
Facility type Street
Type of work Reconstruction
Estimated to start Late June 2017
Estimated to end Early August 2017
Approx. % completed Complete
Consultant MMM Group Limited
Contractor Bayview Construction Ltd
Hiddleston Cr - Cartwright Rd/Jefferson Av   View Map
Facility type Street
Type of work TBO
Estimated to start Early August 2017
Estimated to end Early September 2017
Approx. % completed Complete
Consultant City Of Winnipeg - Streets Maintenance Division
Contractor City Of Winnipeg - Centralized Services
Hugo St S - Arnold Av/Berwick Pl   View Map
Facility type Street
Type of work TBO
Estimated to start Mid June 2017
Estimated to end Late June 2017
Approx. % completed Complete
Consultant City Of Winnipeg - Streets Maintenance Division
Contractor City Of Winnipeg - Centralized Services
Hutton St - Templeton Av/Beecher Av   View Map
Facility type Street
Type of work TBO
Estimated to start Early July 2017
Estimated to end Mid July 2017
Approx. % completed Complete
Consultant KGS Group Limited
Contractor Asphaltec Paving Ltd.
Inkster Bv - 947 Inkster Bv/Wiginton St   View Map
Facility type Street
Type of work Mill and Fill
Estimated to start Early August 2017
Estimated to end Mid August 2017
Approx. % completed Complete
Consultant City Of Winnipeg - Streets Maintenance Division
Contractor City Of Winnipeg - Centralized Services
Jefferson Av/Perth Av - Powers St/Andrews St   View Map
Facility type Alley
Type of work Reconstruction
Estimated to start Early July 2017
Estimated to end Late August 2017
Approx. % completed Complete
Consultant WSP Canada Inc.
Contractor J.C. Paving Ltd.
Jefferson Av/Perth Av - Powers St/Andrews St   View Map
Facility type Alley
Type of work Reconstruction
Estimated to start Late August 2017
Estimated to end Spring 2018
Approx. % completed 50
Consultant WSP Canada Inc.
Contractor Bituminex Paving Ltd
Jefferson Ave - Luzon By/King Edward St   View Map
Facility type Street
Type of work Reconstruction
Estimated to start Late May 2017
Estimated to end Mid July 2017
Approx. % completed Complete
Consultant Stantec
Contractor Bituminex Paving Ltd
Jefferson Avenue and Sinclair Street Intersection   View Map
Facility type Signal
Type of work Full Signal Installation
Estimated to start Early June 2017
Estimated to end Mid October 2017
Approx. % completed Complete
Consultant City of Winnipeg - Transportation Division
Contractor Black & McDonald Limited
Jim Smith Dr - Gateway Rd/End   View Map
Facility type Street
Type of work TBO
Estimated to start Early June 2017
Estimated to end Late June 2017
Approx. % completed Complete
Consultant KGS Group Limited
Contractor Nelson River Construction Inc.
John Hirsch Pl - Rorie St/End   View Map
Facility type Street
Type of work Reconstruction
Estimated to start Mid May 2016
Estimated to end Late July 2017
Approx. % completed Complete
Consultant MMM Group Limited
Contractor Borland Construction
Additional information Click here
Keewatin St - Inkster Bv/Burrows Av   View Map
Facility type Pedestrian / Cycling
Type of work Pedestrian / Cycling - Bi-Directional Pathway Installation
Estimated to start Mid August 2017
Estimated to end Early September 2017
Approx. % completed Complete
Consultant Stantec
Contractor Darco Enterprises Ltd.
Additional information Click here
Kenaston Bv - Bishop Grandin Bv/McGillivray Bv   View Map
Facility type Street
Type of work Street Improvement
Estimated to start Mid August 2017
Estimated to end Late October 2017
Approx. % completed Complete
Consultant Morrison Hershfield Limited
Contractor J.C. Paving Ltd.
Kernaghan Av - Plessis Rd/Robson St   View Map
Facility type Street
Type of work Reconstruction
Estimated to start Mid July 2017
Estimated to end Mid October 2017
Approx. % completed Complete
Consultant MMM Group Limited
Contractor Bayview Construction Ltd
Kildare Av E - Widlake St/Wayoata St   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Mid May 2017
Estimated to end Late June 2017
Approx. % completed Complete
Consultant MMM Group Limited
Contractor Bituminex Paving Ltd
Killkenny Dr - Patricia Av/Radcliffe Rd   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Early August 2016
Estimated to end Late May 2017
Approx. % completed Complete
Consultant AECOM Canada Ltd
Contractor Bayview Construction Ltd
Kingsway - Cambridge St/Oak St   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Early July 2017
Estimated to end Late August 2017
Approx. % completed Complete
Consultant MMM Group Limited
Contractor Bayview Construction Ltd
Kinkora Dr - Southboine Dr/Berkley St N   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Early July 2017
Estimated to end Mid August 2017
Approx. % completed Complete
Consultant AECOM Canada Ltd
Contractor J.C. Paving Ltd.
Kitson St/Hanbury St - Tache Av/Kenny St   View Map
Facility type Alley
Type of work Reconstruction
Estimated to start Mid July 2017
Estimated to end Mid September 2017
Approx. % completed Complete
Consultant WSP Canada Inc.
Contractor J.C. Paving Ltd.
Knotsberry By - Burland Av/Poitras Pl   View Map
Facility type Street
Type of work TBO
Estimated to start Mid May 2017
Estimated to end Early June 2017
Approx. % completed Complete
Consultant KGS Group Limited
Contractor Nelson River Construction Inc.
Kylemore Ave - Daly St S/Osborne St   View Map
Facility type Sidewalk
Type of work Reconstruction
Estimated to start Mid June 2017
Estimated to end Late July 2017
Approx. % completed Complete
Consultant City Of Winnipeg - Engineering Division
Contractor Wintec Building Services Inc.
La Verendrye St - St Joseph St/Tache Av   View Map
Facility type Street
Type of work TBO
Estimated to start Late May 2017
Estimated to end Mid July 2017
Approx. % completed Complete
Consultant City Of Winnipeg - Streets Maintenance Division
Contractor City Of Winnipeg - Centralized Services
La Verendrye St - Thibault St/Langevin St   View Map
Facility type Street
Type of work TBO
Estimated to start Late May 2017
Estimated to end Mid June 2017
Approx. % completed Complete
Consultant City Of Winnipeg - Streets Maintenance Division
Contractor City Of Winnipeg - Centralized Services
Lagimodiere Bv - Dugald Rd/Regent Av W   View Map
Facility type Street
Type of work Mill and Fill
Estimated to start Late July 2017
Estimated to end Late August 2017
Approx. % completed Complete
Consultant Stantec
Contractor Bituminex Paving Ltd
Lagimodiere Bv - Grassie Bv/Grassie Bv   View Map
Facility type Street
Type of work Mill and Fill
Estimated to start Mid July 2017
Estimated to end Early September 2017
Approx. % completed Complete
Consultant City Of Winnipeg - Streets Maintenance Division
Contractor City Of Winnipeg - Centralized Services
Lagimodiere Bv and Sage Creek Bv Intersection   View Map
Facility type Street
Type of work Intersection Improvement
Estimated to start Mid September 2017
Estimated to end Mid October 2017
Approx. % completed Complete
Consultant Stantec
Contractor Bituminex Paving Ltd
Lake Park Dr - Vermillion Rd/Vermillion Rd   View Map
Facility type Street
Type of work TBO
Estimated to start Late May 2017
Estimated to end Late June 2017
Approx. % completed Complete
Consultant KGS Group Limited
Contractor Nelson River Construction Inc.
Lake St - Portage Av/Assiniboine Cr   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Early May 2017
Estimated to end Early May 2017
Approx. % completed Complete
Consultant AECOM Canada Ltd
Contractor J.C. Paving Ltd.
Lakewood Bv - Fermor Av/Weatherstone Pl   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Late July 2017
Estimated to end Late August 2017
Approx. % completed Complete
Consultant AECOM Canada Ltd
Contractor J.C. Paving Ltd.
Lakewood Bv - Weatherstone Pl   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Early August 2016
Estimated to end Late May 2017
Approx. % completed Complete
Consultant AECOM Canada Ltd
Contractor Bayview Construction Ltd
Lancaster Bv - Glastonbury Bv/Aldershot Bv   View Map
Facility type Street
Type of work TBO
Estimated to start Early May 2017
Estimated to end Early June 2017
Approx. % completed Complete
Consultant KGS Group Limited
Contractor Asphaltec Paving Ltd.
Lansdowne Av - McPhillips St/Inkster Bv   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Late May 2017
Estimated to end Early July 2017
Approx. % completed Complete
Consultant City Of Winnipeg - Engineering Division
Contractor Bayview Construction Ltd
Lawndale Av/Birchdale Av - Highfield St/Coniston St   View Map
Facility type Alley
Type of work Reconstruction
Estimated to start Mid July 2017
Estimated to end To Be Determined
Approx. % completed Complete
Consultant WSP Canada Inc.
Contractor Asphaltec Paving Ltd.
Leamen Cr - Doubleday Dr/Pipeline Rd   View Map
Facility type Street
Type of work Reconstruction
Estimated to start Early July 2017
Estimated to end Mid October 2017
Approx. % completed Complete
Consultant MMM Group Limited
Contractor Bituminex Paving Ltd
Leila Av - Sinclair St/Garden Park Dr   View Map
Facility type Street
Type of work Mill and Fill
Estimated to start Early August 2017
Estimated to end Mid August 2017
Approx. % completed Complete
Consultant City Of Winnipeg - Streets Maintenance Division
Contractor City Of Winnipeg - Centralized Services
Lennox Av/Fernwood Av - St Andrew Rd/St Annes Rd   View Map
Facility type Alley
Type of work Reconstruction
Estimated to start Late May 2017
Estimated to end Mid July 2017
Approx. % completed Complete
Consultant WSP Canada Inc.
Contractor J.C. Paving Ltd.
Lenore St - Westminister Av/Wolseley Av   View Map
Facility type Street
Type of work Reconstruction
Estimated to start Early June 2017
Estimated to end Early August 2017
Approx. % completed Complete
Consultant City Of Winnipeg - Engineering Division
Contractor Bayview Construction Ltd
Lewis St/Clarke St - Stradbrook Av/River Av   View Map
Facility type Alley
Type of work Reconstruction
Estimated to start Early July 2017
Estimated to end Spring 2018
Approx. % completed 90
Consultant WSP Canada Inc.
Contractor Bituminex Paving Ltd
Lily St - Market/Galt Av   View Map
Facility type Street
Type of work Reconstruction
Estimated to start Mid May 2016
Estimated to end Late July 2017
Approx. % completed Complete
Consultant MMM Group Limited
Contractor Borland Construction
Additional information Click here
Linden Av - Woodvale St/Henderson Hw   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Early August 2016
Estimated to end Late May 2017
Approx. % completed Complete
Consultant MMM Group Limited
Contractor Bituminex Paving Ltd
Linwood St - Bruce Av/Portage Av   View Map
Facility type Sidewalk
Type of work Reconstruction
Estimated to start Early August 2017
Estimated to end Spring 2018
Approx. % completed 80
Consultant City Of Winnipeg - Engineering Division
Contractor Wintec Building Services Inc.
Lipton St/Ingersoll St - Notre Dame Av/Yarwood Av   View Map
Facility type Alley
Type of work Reconstruction
Estimated to start Early August 2017
Estimated to end Spring 2018
Approx. % completed 80
Consultant WSP Canada Inc.
Contractor J.C. Paving Ltd.
Logan Av - Chambers St/Reitta St   View Map
Facility type Street
Type of work Spot Repairs Addressing Safety Concerns
Estimated to start Early September 2017
Estimated to end Late September 2017
Approx. % completed Complete
Consultant City Of Winnipeg - Streets Maintenance Division
Contractor City Of Winnipeg - Centralized Services
Logan Av/Alexander Av - Laura St/Patrick Av   View Map
Facility type Alley
Type of work Reconstruction
Estimated to start Early August 2017
Estimated to end Mid October 2017
Approx. % completed Complete
Consultant WSP Canada Inc.
Contractor J.C. Paving Ltd.
Loudoun Rd - Wilkes Av/Wyper Rd   View Map
Facility type Street
Type of work Reconstruction
Estimated to start Mid June 2017
Estimated to end Mid October 2017
Approx. % completed 90
Consultant WSP Canada Inc.
Contractor Hugh Munro Construction
Lulu St - Logan Av/Alexander Av   View Map
Facility type Street
Type of work Reconstruction
Estimated to start Late May 2017
Estimated to end Early July 2017
Approx. % completed Complete
Consultant City Of Winnipeg - Engineering Division
Contractor Bayview Construction Ltd
Lyndale Dr - Monck Av/Gauvin St   View Map
Facility type Street
Type of work Reconstruction/Riverbank Stabilization
Estimated to start Late November 2016
Estimated to end Late September 2017
Approx. % completed Complete
Consultant Trek Geotechnical
Contractor Nelson River Construction Inc.
Additional information Click here
Machray Av - Robertson St/Cairnsmore St   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Early August 2016
Estimated to end Late May 2017
Approx. % completed Complete
Consultant AECOM Canada Ltd
Contractor Darco Enterprises Ltd.
Main St - #902 Main St/Euclid Av   View Map
Facility type Street
Type of work Mill and Fill
Estimated to start Mid August 2017
Estimated to end Late August 2017
Approx. % completed Complete
Consultant City Of Winnipeg - Streets Maintenance Division
Contractor City Of Winnipeg - Centralized Services
Manhattan Av - CPR Rail Road Crossing/Grey St   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Early August 2016
Estimated to end Late May 2017
Approx. % completed Complete
Consultant MMM Group Limited
Contractor Bituminex Paving Ltd
Maplehurst Rd - Cottonwood Rd/Monterey Rd   View Map
Facility type Street
Type of work TBO
Estimated to start Late May 2017
Estimated to end Late June 2017
Approx. % completed Complete
Consultant KGS Group Limited
Contractor Nelson River Construction Inc.
Maryland Bridge   View Map
Facility type Bridge
Type of work Bridge Maintenance
Estimated to start Early June 2017
Estimated to end Mid October 2017
Approx. % completed Complete
Consultant Morrison Hershfield Limited
McCreedy Rd - Amelia Cr/Tu Pelo Av   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Mid July 2017
Estimated to end Mid October 2017
Approx. % completed Complete
Consultant MMM Group Limited
Contractor Bayview Construction Ltd
McDermot Ave - 173 McDermot Ave/163 McDermot Ave   View Map
Facility type Sidewalk
Type of work Reconstruction
Estimated to start Early October 2017
Estimated to end Mid October 2017
Approx. % completed 80
Consultant City Of Winnipeg - Engineering Division
Contractor J.C. Paving Ltd.
McGee St - Notre Dame Av/Wellington Av   View Map
Facility type Street
Type of work TBO
Estimated to start Early May 2017
Estimated to end Mid May 2017
Approx. % completed Complete
Consultant KGS Group Limited
Contractor Asphaltec Paving Ltd.
McGillivray Bv - Fennel St/Waverley St   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Late August 2017
Estimated to end Late October 2017
Approx. % completed Complete
Consultant Morrison Hershfield Limited
Contractor J.C. Paving Ltd.
McGillivray Bv - Rapid Transit Corridor Overpass   View Map
Facility type Rapid Transit Corridor
Type of work Rapid Transit - New Overpass Installation
Estimated to start Early May 2017
Estimated to end Late July 2018
Approx. % completed 10
Consultant Plenary Roads
Contractor PCL
Additional information Click here
McPhillips St - Beauty Av/Jefferson Av   View Map
Facility type Street
Type of work Mill and Fill
Estimated to start Late July 2017
Estimated to end Early August 2017
Approx. % completed Complete
Consultant City Of Winnipeg - Streets Maintenance Division
Contractor City Of Winnipeg - Centralized Services
McPhillips St - Mountain Av/Redwood Av   View Map
Facility type Street
Type of work Mill and Fill
Estimated to start Mid August 2017
Estimated to end Early September 2017
Approx. % completed Complete
Consultant Stantec
Contractor Bituminex Paving Ltd
McPhillips St - Redwood Av/College Av   View Map
Facility type Street
Type of work Mill and Fill
Estimated to start Mid August 2017
Estimated to end Early September 2017
Approx. % completed Complete
Consultant Stantec
Contractor Bituminex Paving Ltd
McPhillips St - Storie Rd/150m North of Storie Rd   View Map
Facility type Street
Type of work Mill and Fill
Estimated to start Late August 2017
Estimated to end Mid October 2017
Approx. % completed Complete
Consultant City Of Winnipeg - Streets Maintenance Division
Contractor City Of Winnipeg - Centralized Services
Minto St - St Matthews Av/Molever Av   View Map
Facility type Street
Type of work Reconstruction
Estimated to start Mid July 2017
Estimated to end Early September 2017
Approx. % completed Complete
Consultant City Of Winnipeg - Engineering Division
Contractor Bayview Construction Ltd
Molson St / Panet Rd   View Map
Facility type Street
Type of work Reconstruction
Estimated to start Mid June 2013
Estimated to end Late August 2017
Approx. % completed Complete
Consultant Dillon Consulting Limited
Contractor Bayview Construction Ltd
Additional information Click here
Monck Av/Claremont Av - Kirkdale St/Highfield St   View Map
Facility type Alley
Type of work Reconstruction
Estimated to start Late July 2017
Estimated to end Mid October 2017
Approx. % completed Complete
Consultant WSP Canada Inc.
Contractor Asphaltec Paving Ltd.
Moncton Av - Grey St/Gateway Rd   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start To Be Determined
Estimated to end Mid October 2017
Approx. % completed Complete
Consultant MMM Group Limited
Contractor Bayview Construction Ltd
Monty Hall Dr - Simkin Dr/Oakhurst Cr   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Early August 2016
Estimated to end Mid May 2017
Approx. % completed Complete
Consultant MMM Group Limited
Contractor Bituminex Paving Ltd
Moorgate St - Bruce Av/Lodge Av   View Map
Facility type Street
Type of work Reconstruction
Estimated to start Mid May 2017
Estimated to end Late July 2017
Approx. % completed Complete
Consultant AECOM Canada Ltd
Contractor Maple Leaf Construction Ltd.
Nakomis By - Woodydell Av/Woodydell Av   View Map
Facility type Street
Type of work TBO
Estimated to start Mid May 2017
Estimated to end Late May 2017
Approx. % completed Complete
Consultant KGS Group Limited
Contractor Nelson River Construction Inc.
Ness Av - Olive St/Moray St   View Map
Facility type Street
Type of work Mill and Fill
Estimated to start Late August 2017
Estimated to end Mid September 2017
Approx. % completed Complete
Consultant Stantec
Contractor Bituminex Paving Ltd
Ness Avenue at Sturgeon Creek Bridge   View Map
Facility type Bridge
Type of work Bridge Installation
Estimated to start Early December 2015
Estimated to end Late October 2017
Approx. % completed Complete
Consultant Tetra Tech
Contractor PCL and J.C. Paving Ltd.
Additional information Click here
Newark Rd - Westmount By/Cottonwood Rd   View Map
Facility type Street
Type of work TBO
Estimated to start Late May 2017
Estimated to end Late June 2017
Approx. % completed Complete
Consultant KGS Group Limited
Contractor Nelson River Construction Inc.
Newman Av W - Day St/Bond St   View Map
Facility type Street
Type of work TBO
Estimated to start Early June 2017
Estimated to end Late June 2017
Approx. % completed Complete
Consultant City Of Winnipeg - Streets Maintenance Division
Contractor City Of Winnipeg - Centralized Services
Niagara St - Grosvenor Av/Corydon Av   View Map
Facility type Street
Type of work TBO
Estimated to start Mid June 2017
Estimated to end Early July 2017
Approx. % completed Complete
Consultant City Of Winnipeg - Streets Maintenance Division
Contractor City Of Winnipeg - Centralized Services
Notre Dame Av - Portage Av/Princess St   View Map
Facility type Street
Type of work Reconstruction
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Pre-Construction
Consultant AECOM Canada Ltd
Additional information Click here
Notre Dame Av and Sherburn St Intersection   View Map
Facility type Signal
Type of work Pedestrian Corridor to Half Signal Conversion
Estimated to start Early June 2017
Estimated to end Late October 2017
Approx. % completed Complete
Consultant City of Winnipeg - Transportation Division
Contractor Black & McDonald Limited
Oakenwald Av - North Dr/Point Rd   View Map
Facility type Sidewalk
Type of work Reconstruction
Estimated to start Early August 2017
Estimated to end Late September 2017
Approx. % completed Complete
Consultant City Of Winnipeg - Engineering Division
Contractor Wintec Building Services Inc.
Old Commonwealth Path - Garton Av /Dr Jose Rizal Way   View Map
Facility type Street
Type of work New - Street Installation
Estimated to start Early May 2017
Estimated to end Late May 2017
Approx. % completed Complete
Consultant Stantec
Olive St - Lodge Av/Portage Av   View Map
Facility type Street
Type of work Reconstruction
Estimated to start Late June 2017
Estimated to end Mid October 2017
Approx. % completed Complete
Consultant AECOM Canada Ltd
Contractor J.C. Paving Ltd.
Osborne St and Beresford Av Intersection   View Map
Facility type Signal
Type of work New - Pedestrian Corridor Installation
Estimated to start Early June 2017
Estimated to end Mid October 2017
Approx. % completed Complete
Consultant City of Winnipeg - Transportation Division
Contractor Black & McDonald Limited
Pacific Av - Lily St/Main St   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Summer 2016
Estimated to end Early July 2017
Approx. % completed Complete
Consultant MMM Group Limited
Contractor J.C. Paving Ltd.
Additional information Click here
Paquin Rd - De Baets St/Beghin Av   View Map
Facility type Street
Type of work Reconstruction
Estimated to start Early August 2017
Estimated to end Early November 2017
Approx. % completed Complete
Consultant KGS Group Limited
Contractor Bituminex Paving Ltd
Pembina Hw - Bairdmore Bv/De Vos Rd   View Map
Facility type Street
Type of work Mill and Fill
Estimated to start Early May 2017
Estimated to end Mid October 2017
Approx. % completed Complete
Consultant City Of Winnipeg - Engineering Division
Contractor J.C. Paving Ltd.
Pembina Hw - Cloutier Dr/Ducharme Av   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Early June 2017
Estimated to end Mid July 2017
Approx. % completed Complete
Consultant City Of Winnipeg - Engineering Division
Contractor City Of Winnipeg - Centralized Services
Pembina Hw - Dalhousie Dr/Killarney Av   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Early May 2017
Estimated to end Mid October 2017
Approx. % completed Complete
Consultant City Of Winnipeg - Engineering Division
Contractor J.C. Paving Ltd.
Pembina Hw - De Vos Rd/Dalhousie Dr   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Late August 2017
Estimated to end Mid October 2017
Approx. % completed Complete
Consultant City Of Winnipeg - Engineering Division
Contractor J.C. Paving Ltd.
Pembina Hw - Grant Av/Osborne St   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Early July 2016
Estimated to end Late October 2019
Approx. % completed 90
Consultant MMM Group Limited
Contractor J.C. Paving Ltd.
Additional information Click here
Pembina Hw - Grant Av/Osborne St   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Early July 2016
Estimated to end Late October 2019
Approx. % completed 90
Consultant MMM Group Limited
Contractor J.C. Paving Ltd.
Additional information Click here
Pembina Hw - Killarney Av/Bairdmore Bv   View Map
Facility type Street
Type of work Mill and Fill
Estimated to start Early May 2017
Estimated to end Mid October 2017
Approx. % completed Complete
Consultant City Of Winnipeg - Engineering Division
Contractor J.C. Paving Ltd.
Pembina Hw - Rapid Transit Corridor Underpass   View Map
Facility type Rapid Transit Corridor
Type of work Rapid Transit - New Underpass Installation
Estimated to start Early April 2017
Estimated to end Late November 2019
Approx. % completed 30
Consultant Plenary Roads
Contractor PCL
Additional information Click here
Pine Valley Dr - Country Club Bv/Country Club Bv   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Early August 2016
Estimated to end Late May 2017
Approx. % completed Complete
Consultant AECOM Canada Ltd
Contractor J.C. Paving Ltd.
Pinecrest By - Donwood Dr/Donwood Dr   View Map
Facility type Street
Type of work Reconstruction
Estimated to start Early July 2017
Estimated to end Mid October 2017
Approx. % completed Complete
Consultant MMM Group Limited
Contractor Bayview Construction Ltd
Plessis Rd - Devonshire Dr/100m North Of Kildare Av W   View Map
Facility type Street
Type of work Mill and Fill
Estimated to start Mid June 2017
Estimated to end Late June 2017
Approx. % completed Complete
Consultant City Of Winnipeg - Streets Maintenance Division
Contractor City Of Winnipeg - Centralized Services
Plessis Rd / Gunn Rd   View Map
Facility type Street
Type of work Intersection Improvement
Estimated to start Late August 2017
Estimated to end Late September 2017
Approx. % completed Complete
Consultant MMM Group Limited
Contractor J.C. Paving Ltd.
Portage Av/Wolseley St - Basswood Pl/Newman St   View Map
Facility type Alley
Type of work Reconstruction
Estimated to start Mid May 2017
Estimated to end Late August 2017
Approx. % completed Complete
Consultant WSP Canada Inc.
Contractor J.C. Paving Ltd.
Powers St - Enniskillen Av/Smithfield Av   View Map
Facility type Street
Type of work Reconstruction
Estimated to start Late June 2017
Estimated to end Mid October 2017
Approx. % completed Complete
Consultant MMM Group Limited
Contractor Bituminex Paving Ltd
Princess St - William Av/Donald St   View Map
Facility type Street
Type of work Mill and Fill
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Pre-Construction
Consultant AECOM Canada Ltd
Additional information Click here
Provencher Bv - Des Meurons St/Archibald St   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Mid September 2017
Estimated to end Late October 2017
Approx. % completed Complete
Consultant Stantec
Contractor Bituminex Paving Ltd
Provencher Bv - Langevin St/90m East of Tache Av   View Map
Facility type Street
Type of work Mill and Fill
Estimated to start Mid June 2017
Estimated to end Mid July 2017
Approx. % completed Complete
Consultant City Of Winnipeg - Streets Maintenance Division
Contractor City Of Winnipeg - Centralized Services
Provencher Bv - Tache Av/Langevin St   View Map
Facility type Street
Type of work Mill and Fill
Estimated to start Mid June 2017
Estimated to end Mid July 2017
Approx. % completed Complete
Consultant City Of Winnipeg - Streets Maintenance Division
Contractor City Of Winnipeg - Centralized Services
Rapid Transit Corridor - Phase 2   View Map
Facility type Rapid Transit Corridor
Type of work Rapid Transit - New Rapid Transit Corridor Construction
Estimated to start Summer 2016
Estimated to end Spring 2020
Approx. % completed 10
Consultant Plenary Roads
Contractor PCL
Additional information Click here
Renfrew By Alley   View Map
Facility type Alley
Type of work Reconstruction
Estimated to start Early July 2017
Estimated to end Mid October 2017
Approx. % completed Complete
Consultant WSP Canada Inc.
Contractor Bituminex Paving Ltd
Roblin Bv - Barnstaple Cv/Fairmont Rd   View Map
Facility type Street
Type of work Mill and Fill
Estimated to start Mid August 2017
Estimated to end Late August 2017
Approx. % completed Complete
Consultant City Of Winnipeg - Streets Maintenance Division
Contractor City Of Winnipeg - Centralized Services
Roslyn Rd - Osborne St/End   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Early August 2017
Estimated to end Mid September 2017
Approx. % completed Complete
Consultant MMM Group Limited
Contractor Bayview Construction Ltd
Rue Des Trappistes at Westendorf Coulee Culvert Replacement and Road Reconstruction Rue Du Monastere to Pembina Hwy   View Map
Facility type Bridge
Type of work New - Culvert Installation
Estimated to start Late November 2017
Estimated to end Summer 2018
Approx. % completed 0
Sackville St - Ness Av/Bruce Av   View Map
Facility type Street
Type of work TBO
Estimated to start Early June 2017
Estimated to end Late June 2017
Approx. % completed Complete
Consultant City Of Winnipeg - Streets Maintenance Division
Contractor City Of Winnipeg - Centralized Services
Salter St - Inkster Bv/Cathedral Av   View Map
Facility type Street
Type of work Reconstruction
Estimated to start Early July 2017
Estimated to end Early November 2017
Approx. % completed Complete
Consultant Morrison Hershfield Limited
Contractor Borland Construction
Salter St - Leila Av/Partridge Av   View Map
Facility type Street
Type of work Mill and Fill
Estimated to start Late July 2017
Estimated to end Mid August 2017
Approx. % completed Complete
Consultant City Of Winnipeg - Streets Maintenance Division
Contractor City Of Winnipeg - Centralized Services
Salter St and Church Av Intersection   View Map
Facility type Signal
Type of work New - Pedestrian Corridor Installation
Estimated to start Early June 2017
Estimated to end Late October 2017
Approx. % completed Complete
Consultant City of Winnipeg - Transportation Division
Contractor Black & McDonald Limited
Sandpiper Dr - Bairdmore Bv/Point West Dr   View Map
Facility type Street
Type of work TBO
Estimated to start Mid May 2017
Estimated to end Early June 2017
Approx. % completed Complete
Consultant KGS Group Limited
Contractor Asphaltec Paving Ltd.
Sargent Park Pl - Dominion St/Downing St   View Map
Facility type Street
Type of work Reconstruction
Estimated to start Early July 2017
Estimated to end Mid August 2017
Approx. % completed Complete
Consultant City Of Winnipeg - Engineering Division
Contractor Bayview Construction Ltd
Sasaki Cr - Sorokin St/Adsum Dr   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Late June 2017
Estimated to end Mid October 2017
Approx. % completed Complete
Consultant MMM Group Limited
Contractor Bituminex Paving Ltd
Savoy Cr- N End/Scottswood Dr   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Early July 2017
Estimated to end Late October 2017
Approx. % completed Complete
Consultant AECOM Canada Ltd
Contractor J.C. Paving Ltd.
Shaftesbury Bv - Corydon Av/Mountbatten Av   View Map
Facility type Street
Type of work Mill and Fill
Estimated to start Early August 2017
Estimated to end Mid August 2017
Approx. % completed Complete
Consultant City Of Winnipeg - Streets Maintenance Division
Contractor City Of Winnipeg - Centralized Services
Shaftsbury Bv - Grant Av/West Taylor Bv   View Map
Facility type Sidewalk
Type of work Reconstruction
Estimated to start Early July 2017
Estimated to end Mid August 2017
Approx. % completed Complete
Consultant City Of Winnipeg - Engineering Division
Contractor J.C. Paving Ltd.
Sherbrook St - McDermot Av/Cumberland Av   View Map
Facility type Street
Type of work Mill and Fill
Estimated to start Early June 2017
Estimated to end Late October 2017
Approx. % completed 10
Consultant Stantec
Contractor Darco Enterprises Ltd.
Silverstone Av - Cornell Dr/Kings Dr   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Late June 2017
Estimated to end Early August 2017
Approx. % completed Complete
Consultant MMM Group Limited
Contractor Bayview Construction Ltd
Sinclair St - Selkirk Av/Jarvis Av   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Early July 2017
Estimated to end Mid October 2017
Approx. % completed Complete
Consultant MMM Group Limited
Contractor Darco Enterprises Ltd.
Somerville Av/Somerset Av - Riverside Dr/Point Rd   View Map
Facility type Alley
Type of work Reconstruction
Estimated to start Early June 2017
Estimated to end Spring 2018
Approx. % completed 90
Consultant WSP Canada Inc.
Contractor Asphaltec Paving Ltd.
Sorokin St - Adsum Dr/Margate Rd   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Late June 2017
Estimated to end Mid October 2017
Approx. % completed Complete
Consultant MMM Group Limited
Contractor Bituminex Paving Ltd
South Dr - Wildwood St/Point Rd   View Map
Facility type Street
Type of work Reconstruction
Estimated to start Late August 2016
Estimated to end Late May 2017
Approx. % completed Complete
Consultant Morrison Hershfield Limited
Contractor Maple Leaf Construction Ltd.
Speers Rd - Cottonwood Rd/Crestwood Cr   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Late August 2017
Estimated to end Late October 2017
Approx. % completed 10
Consultant AECOM Canada Ltd
Contractor J.C. Paving Ltd.
Springlea Pa - Morningmead Wk/Gilmore Av   View Map
Facility type Street
Type of work TBO
Estimated to start Early June 2017
Estimated to end Late June 2017
Approx. % completed Complete
Consultant KGS Group Limited
Contractor Nelson River Construction Inc.
St Anthony Av/Jefferson Av - McGregor St/McKenzie St   View Map
Facility type Alley
Type of work Reconstruction
Estimated to start Early May 2017
Estimated to end Early June 2017
Approx. % completed Complete
Consultant WSP Canada Inc.
Contractor J.C. Paving Ltd.
St Dunstans By - Dalhousie Dr/Dalhousie Dr   View Map
Facility type Street
Type of work TBO
Estimated to start Mid May 2017
Estimated to end Early June 2017
Approx. % completed Complete
Consultant KGS Group Limited
Contractor Asphaltec Paving Ltd.
St James St - Maroons Rd/Ness Av   View Map
Facility type Street
Type of work Reconstruction
Estimated to start Early May 2017
Estimated to end Late September 2017
Approx. % completed Complete
Consultant Morrison Hershfield Limited
Contractor Maple Leaf Construction Ltd.
St James St - Ness Av/Portage Av   View Map
Facility type Street
Type of work Reconstruction
Estimated to start Early May 2017
Estimated to end Late September 2017
Approx. % completed Complete
Consultant Morrison Hershfield Limited
Contractor Maple Leaf Construction Ltd.
St Matthews Av - Century St/Berry St   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Late August 2017
Estimated to end Early June 2018
Approx. % completed Complete
Consultant KGS Group Limited
Contractor Bituminex Paving Ltd
St Matthews Av - Dominion St/Goulding St   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Early May 2017
Estimated to end Late June 2017
Approx. % completed Complete
Consultant AECOM Canada Ltd
Contractor Bayview Construction Ltd
St Matthews Av - Ferry Rd/Berry St   View Map
Facility type Street
Type of work Reconstruction
Estimated to start Mid August 2017
Estimated to end Early Spring 2018
Approx. % completed Complete
Consultant KGS Group Limited
Contractor Bituminex Paving Ltd
St. Vital Trail - Ashford Dr/Paddington Rd   View Map
Facility type Pedestrian / Cycling
Type of work Pedestrian / Cycling - Path Renewal
Estimated to start Mid July 2017
Estimated to end Early August 2017
Approx. % completed Complete
Consultant City Of Winnipeg - Engineering Division
Contractor L.Chabot Enterprises Ltd.
St. Vital Trail - Paddington Rd/St Marys Rd   View Map
Facility type Pedestrian / Cycling
Type of work Pedestrian / Cycling - Path Renewal
Estimated to start Mid July 2017
Estimated to end Early August 2017
Approx. % completed Complete
Consultant City Of Winnipeg - Engineering Division
Contractor L.Chabot Enterprises Ltd.
St. Vital Trail - St Annes Rd/Ashworth St S   View Map
Facility type Pedestrian / Cycling
Type of work Pedestrian / Cycling - Path Renewal
Estimated to start Mid July 2017
Estimated to end Early August 2017
Approx. % completed Complete
Consultant City Of Winnipeg - Engineering Division
Contractor L.Chabot Enterprises Ltd.
St.Vital Bridge   View Map
Facility type Bridge
Type of work Bridge Maintenance
Estimated to start Early May 2017
Estimated to end Late May 2017
Approx. % completed Complete
Consultant Dillon Consulting Limited
Contractor Gateway Construction & Engineering Ltd.
Stonebridge Ln - Mosswood Pl/Dale Bv   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Mid May 2017
Estimated to end Late June 2017
Approx. % completed Complete
Consultant AECOM Canada Ltd
Contractor Maple Leaf Construction Ltd.
Stradbrook Av - Scott St/Osborne St   View Map
Facility type Street
Type of work Mill and Fill
Estimated to start Mid August 2017
Estimated to end Early October 2017
Approx. % completed Complete
Consultant City Of Winnipeg - Streets Maintenance Division
Contractor City Of Winnipeg - Centralized Services
Tache Av and De La Cathedrale Av Intersection   View Map
Facility type Signal
Type of work New - Pedestrian Corridor Installation
Estimated to start Early June 2017
Estimated to end Mid October 2017
Approx. % completed Complete
Consultant City of Winnipeg - Transportation Division
Contractor Black & McDonald Limited
Tanoak Park Dr - Hillhouse Rd/Hillhouse Rd   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Late June 2017
Estimated to end Mid October 2017
Approx. % completed Complete
Consultant MMM Group Limited
Contractor Darco Enterprises Ltd.
Thomas Berry St - East End/Traverse Av   View Map
Facility type Street
Type of work TBO
Estimated to start Early June 2017
Estimated to end Mid June 2017
Approx. % completed Complete
Consultant KGS Group Limited
Contractor Nelson River Construction Inc.
Thomas Berry St - Traverse Av/W End   View Map
Facility type Street
Type of work TBO
Estimated to start Early June 2017
Estimated to end Mid June 2017
Approx. % completed Complete
Consultant KGS Group Limited
Contractor Nelson River Construction Inc.
Torwood Cr - Tallman St/Barnham Cr   View Map
Facility type Street
Type of work TBO
Estimated to start Early July 2017
Estimated to end Mid July 2017
Approx. % completed Complete
Consultant KGS Group Limited
Contractor Asphaltec Paving Ltd.
Transcona Bv - Burnaby By/380m West of Bienvenue St   View Map
Facility type Street
Type of work New - Twinning of Street
Approx. % completed Complete
Consultant Stantec
Additional information Click here
Transcona Trail - Regent Ave W/Panet Rd   View Map
Facility type Pedestrian / Cycling
Type of work Pedestrian / Cycling - New Multi-Use Pathway Installation
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Pre-Construction
Consultant Stantec
Contractor Darco Enterprises Ltd.
Vanderbilt Dr - Fleetwood Rd/Scurfield Bv   View Map
Facility type Street
Type of work TBO
Estimated to start Mid May 2017
Estimated to end Early June 2017
Approx. % completed Complete
Consultant KGS Group Limited
Contractor Asphaltec Paving Ltd.
Vermillion Rd - Beaverhill Bv/Lakewood Bv   View Map
Facility type Sidewalk
Type of work New - Sidewalk Installation
Estimated to start Early July 2017
Estimated to end Early August 2017
Approx. % completed Complete
Consultant City Of Winnipeg - Engineering Division
Contractor Darco Enterprises Ltd.
Wall St - Sargent Av/Ellice Av   View Map
Facility type Street
Type of work Mill and Fill
Estimated to start Late September 2017
Estimated to end Early October 2017
Approx. % completed Complete
Consultant City Of Winnipeg - Streets Maintenance Division
Contractor City Of Winnipeg - Centralized Services
Waterloo St/Ash St - Academy Rd/Kingsway   View Map
Facility type Alley
Type of work Reconstruction
Estimated to start Late July 2017
Estimated to end Spring 2018
Approx. % completed 90
Consultant WSP Canada Inc.
Contractor Bituminex Paving Ltd
Waverley St/Oxford St - Academy Rd/Kingsway   View Map
Facility type Alley
Type of work Reconstruction
Estimated to start Early August 2017
Estimated to end Mid October 2017
Approx. % completed Complete
Consultant WSP Canada Inc.
Contractor Bituminex Paving Ltd
Waverley Underpass Project - Taylor Av / Waverley St / Wilkes Av / Grant Av   View Map
Facility type Street
Type of work Reconstruction/Rehabilitation
Estimated to start Early May 2017
Estimated to end Mid October 2019
Approx. % completed 10
Consultant Dillon Consulting Limited
Contractor Maple Leaf Construction Ltd.
Additional information Click here
Waverley Underpass Project - Taylor Av / Waverley St / Wilkes Av / Grant Av   View Map
Facility type Bridge
Type of work New - Underpass Installation
Estimated to start Early May 2017
Estimated to end Mid October 2019
Approx. % completed 10
Consultant Dillon Consulting Limited
Contractor Maple Leaf Construction Ltd.
Additional information Click here
Weatherstone Pl - Lakewood Bv/Pebble Beach Rd   View Map
Facility type Sidewalk
Type of work New - Sidewalk Installation
Estimated to start Late June 2017
Estimated to end Mid July 2017
Approx. % completed Complete
Consultant City Of Winnipeg - Engineering Division
Contractor Darco Enterprises Ltd.
Weaver By - Pulberry St/Parkville Dr   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Late May 2017
Estimated to end Late August 2017
Approx. % completed Complete
Consultant Morrison Hershfield Limited
Contractor Maple Leaf Construction Ltd.
Webb Pl - Vaughan St/Colony St   View Map
Facility type Street
Type of work TBO
Estimated to start Early June 2017
Estimated to end Mid June 2017
Approx. % completed Complete
Consultant KGS Group Limited
Contractor Asphaltec Paving Ltd.
West Alexander Pedestrian and Cycling Corridor   View Map
Facility type Pedestrian / Cycling
Type of work Pedestrian / Cycling - New Protected Bike Lane Installation
Estimated to start Mid August 2017
Estimated to end Late October 2017
Approx. % completed 10
Consultant Stantec
Contractor Darco Enterprises Ltd.
Additional information Click here
West Alexander Pedestrian and Cycling Corridor   View Map
Facility type Pedestrian / Cycling
Type of work Pedestrian / Cycling - New Protected Bike Lane Installation
Estimated to start Late August 2017
Estimated to end Early Spring 2018
Approx. % completed 80
Consultant Stantec
Contractor Darco Enterprises Ltd.
Additional information Click here
Westway - Empress St E/Empress St   View Map
Facility type Street
Type of work Mill and Fill
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Pre-Construction
Consultant Morrison Hershfield Limited
Additional information Click here
Westwood Dr - Byrd Av/Sansome Av   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Early July 2017
Estimated to end Mid October 2017
Approx. % completed Complete
Consultant AECOM Canada Ltd
Contractor J.C. Paving Ltd.
Westwood Dr - Sansome Av/Byrd Av   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Early July 2017
Estimated to end Mid October 2017
Approx. % completed Complete
Consultant AECOM Canada Ltd
Contractor J.C. Paving Ltd.
William Av - Kate St/Adelaide St   View Map
Facility type Sidewalk
Type of work Reconstruction
Estimated to start Early July 2017
Estimated to end Mid August 2017
Approx. % completed Complete
Consultant City Of Winnipeg - Engineering Division
Contractor J.C. Paving Ltd.
William Av/Elgin Av - Gertie St/Ellen St   View Map
Facility type Alley
Type of work Reconstruction
Estimated to start Early July 2017
Estimated to end Mid October 2017
Approx. % completed Complete
Consultant WSP Canada Inc.
Contractor J.C. Paving Ltd.
Winslow Dr - Riel Av/Harry Collins Av   View Map
Facility type Street
Type of work TBO
Estimated to start Late May 2017
Estimated to end Early July 2017
Approx. % completed Complete
Consultant KGS Group Limited
Contractor Nelson River Construction Inc.
Woodvale St - Oakview Av/Helmsdale Av   View Map
Facility type Street
Type of work TBO
Estimated to start Late June 2017
Estimated to end Mid July 2017
Approx. % completed Complete
Consultant KGS Group Limited
Contractor Nelson River Construction Inc.

Disclaimer and Indemnity:

The information on this web site is provided as a public service and should be used for general information purposes only. Although the information provided represents the planned capital work on city infrastructure for the current year, the City of Winnipeg cannot guarantee that it is accurate or current at all times. Although it is rare that projects are not finished within the stated timeframe, the City cannot guarantee that the work will be completed in all cases.

The information on this web site is subject to change without notice. Winnipeg.ca AND ITS AFFILIATES ARE NOT RESPONSIBLE IN ANY MANNER FOR DIRECT, INDIRECT, SPECIAL OR CONSEQUENTIAL DAMAGES HOWSOEVER CAUSED RESULTING FROM THE USE, MISUSE OR MISINTERPRETATION OF ANY CONTENT, PRODUCTS OR SERVICES PROVIDED BY THIS WEB SITE.

By using this site, you agree to indemnify, defend and hold harmless City of Winnipeg and its officials, officers, employees and authorized representatives from and against any liability, loss injury (including injuries resulting in death), demand, action, cost, expense, or claim of any kind, including but not limited to lawyer's fees, relating in any way to your use of the contents, or services provided by this web site.