Site Accessibility Information Access Key 1 to Skip to Top Navigation Access Key 2 to Skip to the Three One One link Access Key 3 to Skip to City of Winnipeg Main Menu Access Key 4 to Skip to Left Navigation Menu Access Key 5 to Skip to Content area Access Key 6 to Skip to Right Sidebar content area Access Key 7 to Skip to Footer Links
City of Winnipeg
|  Link to the City of Winnipeg French websiteFrançais  |
Until Election Day
on October 24
City services in the event of a Canada Post work stoppage

Community Services

Accessibility

Pam Am Pool Ceiling, Lighting and Public Address System Replacement Project

Update October 2018 – The City of Winnipeg awarded a construction contract to Jilmark Construction Ltd. for the renewal of the end-of-life ceiling acoustic tiles, lighting and public address system at Pan Am Pool. The entire facility was closed from July 30 until October 4 to allow for safe progress on this work as well as completion of several other concurrent facility renewal projects.

On October 5, 2018, the following areas of the facility were re-opened to the public:

  • Training tank
  • Kiddie pool
  • Public change facilities
  • Upper weight room
  • Portions of the walking track
  • Upper training tank observation section
  • Front lobby and adjacent auxiliary rooms

Background

The Pan Am Pool, Winnipeg’s premier aquatic facility, is set to receive a major capital investment beginning in summer 2018, as work is undertaken to replace the pool’s 51-year-old ceiling, lighting, and public address system.

Replacement of these important interior components will cost approximately $3.4 million and will ensure that the Pan Am Pool remains a safe and enjoyable facility for many years to come. The Public Service is working collaboratively with Pan Am Pool user groups to minimize the impact of this closure.

Frequently Asked Questions

Open all | Close all

What is wrong with the pool’s existing ceiling, lighting and PA system?

A study was completed in November 2017 to assess the ceiling tiles, lighting and public address system. Inspections of the t-bar system supporting the acoustic tiles in Pan Am Pool revealed corrosion due to the high humidity and corrosive pool environment. As these tiles contain asbestos, there is significant risk associated with this issue and the tiles will need to be removed and replaced.

In addition to the structural concerns noted above, acoustic testing by the consultant indicates better acoustic levels can be achieved if the existing asbestos tiles are replaced, providing better sound attenuation for customers, user groups and facility staff. A new acoustic ceiling system and additional sound attenuation on key walls is recommended.

Further testing during a consultant study indicated that lighting levels in this facility are low and should be improved.

The facility public address system, which is mounted within the Pan Am ceiling, is now 51 years old, has been repaired on numerous occasions and has experienced several points of failure. As the pulic address system is required for both programmed events and facility safety announcements, it is imperative that it be replaced as part of the ceiling and lighting work.

Will Pan Am Pool have to close to complete this project?

City officials will work to open sections of the facility during construction when safe to do so. To help minimize effects of the closure on sport clubs, swimming lesson participants, active living members, general use patrons and private service providers, the Public Service is working to identify other City pool and recreation locations with available space.

How will the City prioritize Pan Am Pool user groups when allocating available space at alternate locations?

Existing programs and services at alternative pool locations will largely, remain unaffected. User groups displaced due to the Pan Am Pool main tank closure have been offered some alternative pool locations based on availability and required amenities.

What is the budget for this capital project?

The project budget is expected to be approx. $3.4M which includes construction, consulting costs, fees, and a construction contingency.

Documents

Document Name Date Type
RFP 963-2017 2018-01-23 (Closing date) RFP
News Release 2018-02-15 News Release
News Release 2018-7-27 News Release
News Release 2018-10-03 News Release
Last update: October 4, 2018