Site Accessibility Information Access Key 1 to Skip to Top Navigation Access Key 2 to Skip to the Three One One link Access Key 3 to Skip to City of Winnipeg Main Menu Access Key 4 to Skip to Left Navigation Menu Access Key 5 to Skip to Content area Access Key 6 to Skip to Right Sidebar content area Access Key 7 to Skip to Footer Links
City of Winnipeg
|  Link to the City of Winnipeg French websiteFrançais  |
Until Election Day
on October 24

Public Works

Road Construction List

The roadway construction list provides project information in alphabetical order by street name. Project information is available by location in both map and list format. Please see the regional street lane closures page for information on current lane closures on major streets.

How to use the construction list

Click on the + beside the project name. A dropdown box will appear with these project details:

  1. type of infrastructure (street, alley, sidewalk, traffic signal, bridge project, pedestrian and cycling path),
  2. type of construction work (reconstruction, rehabilitation, mill & fill, thin bituminous overlay, improvements within the right-of-way)
  3. estimated to start,
  4. estimated to end,
  5. approximate percentage completed:
    • Pre-Construction – Construction phase has not started.
    • 0% – Construction contract is in place, but crews have not mobilized to the site.
    • 5% – Crews have mobilized to the site and construction has just begun.
    • 10% 90% – An approximation of progress; construction is well underway.
    • 95% – Main roadway construction is complete; travelling lanes are open/parking is restored/garbage pickup resumes (depending on the location); minor deficiencies and landscaping (seeding/sod) are likely outstanding.
    • COMPLETE – All construction components of the project are complete. Contractor may return for any follow up or warranty work in the next 1-2 years. Utilities (e.g. street lights) may or may not be complete. Construction may not be complete for other locations in the same contract.
  6. consultant information, and
  7. contractor information.

You can also view projects by street name using the Search box provided. Click "View Map" beside any project name to view in a map.

Note: As construction projects get underway this season the information about start dates and completion dates will be updated to reflect the actual project timeline.

A   B   C   D   E   F   G   H   I   J   K   L   M   N   O   P   Q   R   S   T   U   V   W   X   Y   Z


City of Winnipeg - Public Works Capital Projects
(Last updated on August 17, 2018 @ 8:00 PM)
 
 
View All on Map


Academy Rd - Waverley St/ Ash St   View Map
Facility type Sidewalk
Type of work Reconstruction
Estimated to start Late June 2018
Estimated to end Mid July 2018
Approx. % completed Planned
Consultant City Of Winnipeg - Engineering Division
Academy Rd/Kingsway Af-Cambridge St/Oxford St   View Map
Facility type Alley
Type of work Reconstruction
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Consultant WSP Canada Inc.
Contractor Bituminex Paving Ltd
Agnes Arnold Pl - Leila Av/Roberts Cr   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Early August 2018
Estimated to end Late September 2018
Approx. % completed 45
Consultant City Of Winnipeg - Engineering Division
Contractor Darco Enterprises Ltd.
Aikins St - North End/Templeton Av   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Pre-Construction
Consultant WSP Canada Inc.
Alexander Av - Ellen St/Isabel St   View Map
Facility type Street
Type of work TBO
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Consultant WSP Canada Inc.
Amanda Cr - Templeton Av/Sinclair St   View Map
Facility type Street
Type of work TBO
Estimated to start To Be Determined
Estimated to end Mid July 2018
Approx. % completed Complete
Consultant City Of Winnipeg - Streets Maintenance Division
Contractor City Of Winnipeg - Centralized Services
Angus St - Rover Av/Sutherland Av   View Map
Facility type Street
Type of work TBO
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Consultant WSP Canada Inc.
Archibald St/Elizabeth Rd   View Map
Facility type Signal
Type of work Signal Improvements
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Arlington St - Ellice Av/St Matthews Av   View Map
Facility type Sidewalk
Type of work Reconstruction
Estimated to start Late August 2018
Estimated to end Mid September 2018
Approx. % completed Planned
Consultant City Of Winnipeg - Engineering Division
Arlington St - Sargent Av/Ellice Av   View Map
Facility type Sidewalk
Type of work Reconstruction
Estimated to start Late August 2018
Estimated to end Mid September 2018
Approx. % completed Planned
Consultant City Of Winnipeg - Engineering Division
Arthur St - McDermot Av/Notre Dame Av   View Map
Facility type Street
Type of work New Facility - Painted Bike Lane
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Consultant AECOM Canada Ltd
Contractor J.C. Paving Ltd.
Arthur St/McDermot Av   View Map
Facility type Signal
Type of work Signal Improvements
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Ashburn St - Sargent Av/Ellice Av   View Map
Facility type Street
Type of work Reconstruction
Estimated to start Mid July 2018
Estimated to end Early September 2018
Approx. % completed 5
Consultant Morrison Hershfield Limited
Contractor Bayview Construction Ltd
Assiniboine Park Dr - Roblin Bv/Commissary Rd   View Map
Facility type Street
Type of work Reconstruction
Estimated to start Mid May 2018
Estimated to end Mid October 2018
Approx. % completed 10
Consultant City Of Winnipeg - Engineering Division
Contractor Bituminex Paving Ltd
Aubert St - St Joseph St/Tache Av   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Consultant WSP Canada Inc.
Bannerman Av - Airlies St/McPhillips St   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Mid May 2018
Estimated to end Early July 2018
Approx. % completed 70
Consultant City Of Winnipeg - Engineering Division
Contractor Darco Enterprises Ltd.
Banning St/Lipton St - Notre Dame Av/Yarwood Av   View Map
Facility type Alley
Type of work Reconstruction
Estimated to start Mid May 2018
Estimated to end Late May 2018
Approx. % completed Complete
Consultant WSP Canada Inc.
Contractor J.C. Paving Ltd.
Barbara Cr - Norlorne Dr/Norlorne Dr   View Map
Facility type Street
Type of work TBO
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Pre-Construction
Consultant WSP Canada Inc.
Bayne Cr- London St/Tu Pelo Av   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Pre-Construction
Consultant WSP Canada Inc.
Beghin Av - Dugald Rd/De Baets St   View Map
Facility type Street
Type of work Reconstruction
Estimated to start Late May 2018
Estimated to end Mid June 2018
Approx. % completed Complete
Consultant KGS Group Limited
Contractor Bayview Construction Ltd
Beresford Av - Osborne St/Daly St S   View Map
Facility type Street
Type of work Reconstruction
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Pre-Construction
Consultant WSP Canada Inc.
Contractor J.C. Paving Ltd.
Best St - Portage Av/Allard Av   View Map
Facility type Street
Type of work TBO
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Consultant WSP Canada Inc.
Bethune Wy - Wright St/Darwin St   View Map
Facility type Street
Type of work TBO
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Consultant WSP Canada Inc.
Bingham Dr - Rannock Av/Rannock Av   View Map
Facility type Street
Type of work TBO
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Pre-Construction
Consultant WSP Canada Inc.
Binscarth St - McMeans Av E/Kildare Av E   View Map
Facility type Street
Type of work TBO
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Consultant WSP Canada Inc.
Bishop Grandin Bv - Rapid Transit Corridor Overpass   View Map
Facility type Bridge
Type of work New - Rapid Transit Overpass Installation
Estimated to start Early February 2017
Estimated to end Late September 2018
Approx. % completed 10
Consultant Plenary Roads
Contractor PCL
Additional information Click here
Bishop Grandin Bv/Kenaston Bv   View Map
Facility type Signal
Type of work Signal Improvements
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Bison Dr/80m West of Pembina Hw   View Map
Facility type Signal
Type of work Signal Improvements
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Blue Mountain Rd - Royal Park Cr/Royal Mint Dr   View Map
Facility type Street
Type of work TBO
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Consultant WSP Canada Inc.
Bournais Dr - Railway Crossing/Dugald Rd   View Map
Facility type Street
Type of work Reconstruction
Estimated to start Late August 2017
Estimated to end Early November 2017
Approx. % completed Complete
Consultant KGS Group Limited
Contractor Bayview Construction Ltd
Bridgecrest Dr - Wynford Dr/St Martin Bv   View Map
Facility type Street
Type of work TBO
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Complete
Consultant City Of Winnipeg - Streets Maintenance Division
Contractor City Of Winnipeg - Centralized Services
Brighton Ct/Kildare Av E-Southampton Pl/Wayoata St   View Map
Facility type Alley
Type of work Reconstruction
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Consultant WSP Canada Inc.
Contractor J.C. Paving Ltd
Broadway - Sherbrook St/Portage Av   View Map
Facility type Street
Type of work Mill and Fill
Estimated to start Early September 2017
Estimated to end Late September 2017
Approx. % completed Complete
Consultant Stantec Consulting Ltd.
Contractor Bituminex Paving Ltd
Broadway/Garry St   View Map
Facility type Signal
Type of work Signal Improvements
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Bronstone Bv/West Fernwood Av - Bronstone Bv/St Marys Rd   View Map
Facility type Alley
Type of work Reconstruction
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed 0
Consultant WSP Canada Inc.
Contractor Asphaltec Paving Ltd.
Brookside Bv/Jefferson Av   View Map
Facility type Signal
Type of work Signal Improvements
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Bruce Av - Ferry Rd/Amherst St   View Map
Facility type Sidewalk
Type of work Reconstruction
Estimated to start Early June 2018
Estimated to end Late June 2018
Approx. % completed 95
Consultant City Of Winnipeg - Engineering Division
Contractor Wintec Building Service Inc.
Bruce Av - Woodlawn St/Conway St   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed 10
Consultant AECOM Canada Ltd
Contractor Borland Construction Inc.
Buchanan Bv - Saskatchewan Av/Peltier Av   View Map
Facility type Sidewalk
Type of work Sidewalk Reconstruction
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Consultant City Of Winnipeg - Engineering Division
Budden Dr - Tu Pelo Av/Gateway Rd   View Map
Facility type Street
Type of work TBO
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Complete
Consultant City Of Winnipeg - Streets Maintenance Division
Contractor City Of Winnipeg - Centralized Services
Burrows Avv- Powers St/Aikins St   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Consultant Morrison Hershfield Limited
Contractor Bayview Construction Ltd
Byng Pl/90m West of Pembina Hw   View Map
Facility type Signal
Type of work Signal Improvements
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Cail By - Jefferson Av/Jefferson Av   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Early June 2018
Estimated to end Late July 2018
Approx. % completed 65
Consultant City Of Winnipeg - Engineering Division
Contractor Darco Enterprises Ltd.
Calrossie Bv/Byng Pl - Riverside Dr/Pembina Hw   View Map
Facility type Alley
Type of work Reconstruction
Estimated to start Mid May 2018
Estimated to end To be determined
Approx. % completed Complete
Consultant WSP Canada Inc.
Contractor Asphaltec Paving Ltd.
Carlton St - Backlane South of Broadway/Assiniboine Av/Assiniboine Av   View Map
Facility type Sidewalk
Type of work Reconstruction
Estimated to start Mid May 2018
Estimated to end Mid June 2018
Approx. % completed Planned
Consultant City Of Winnipeg - Engineering Division
Carlton St - Backlane South of Broadway/Assiniboine Av/Assiniboine Av   View Map
Facility type Sidewalk
Type of work Reconstruction
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Consultant City Of Winnipeg - Engineering Division
Carlton St - Portage Av/Graham Av   View Map
Facility type Sidewalk
Type of work Reconstruction
Estimated to start Mid June 2018
Estimated to end Early July 2018
Approx. % completed Planned
Consultant City Of Winnipeg - Engineering Division
Carmarthen Bv - Devonport Bv/Birkenhead Av   View Map
Facility type Street
Type of work TBO
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Pre-Construction
Consultant WSP Canada Inc.
Carriage Rd- 145 Carriage Rd/Thornton Av   View Map
Facility type Sidewalk
Type of work Reconstruction
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Consultant City Of Winnipeg - Engineering Division
Century St/Ellice Av   View Map
Facility type Signal
Type of work Signal Improvements
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Chambers St - Logan Av/Alexander Av   View Map
Facility type Street
Type of work Reconstruction
Estimated to start Mid May 2018
Estimated to end Early July 2018
Approx. % completed 95
Consultant City Of Winnipeg - Engineering Division
Contractor Darco Enterprises Ltd.
Chevrier Bv - Pembina Hw/Trottier By   View Map
Facility type Street
Type of work Reconstruction
Estimated to start Mid May 2018
Estimated to end Mid October 2018
Approx. % completed 40
Consultant WSP Canada Inc.
Contractor Bayview Construction Ltd
Chevrier Bv - Trottier By/Waverley St   View Map
Facility type Street
Type of work Mill and Fill - Pavement Widening
Estimated to start Mid May 2018
Estimated to end Mid October 2018
Approx. % completed 40
Consultant WSP Canada Inc.
Contractor Bayview Construction Ltd
Chief Peguis Greenway Extension   View Map
Facility type Pedestrian / Cycling
Type of work New - Pedestrian / Cycling Construction
Estimated to start Mid April 2018
Estimated to end July 2019
Approx. % completed 50
Consultant WSP Canada Inc.
Contractor J.C. Paving Ltd.
Additional information Click here
Chief Peguis Greenway Extension   View Map
Facility type Signal
Type of work Signal Improvements
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Churchill Dr - Eccles St/Casey St   View Map
Facility type Street
Type of work Reconstruction
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed 5
Consultant WSP Canada Inc.
Contractor J.C. Paving Ltd.
Colby Av - Shore St/Barnes St   View Map
Facility type Street
Type of work TBO
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Consultant WSP Canada Inc.
Colleen Rd - Mac St/Jones St   View Map
Facility type Street
Type of work Reconstruction
Estimated to start Early July 2018
Estimated to end To Be Determined
Approx. % completed 30
Consultant Morrison Hershfield Limited
Contractor Bayview Construction Ltd
Colony St - Ellice Av/Portage Av   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Pre-Construction
Consultant WSP Canada Inc.
Coniston St/Lyndale Dr - Claremont Av/Ferndale Av   View Map
Facility type Alley
Type of work Reconstruction
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Consultant WSP Canada Inc.
Coniston St/Lyndale Dr - Crawford Av/Tache Av   View Map
Facility type Alley
Type of work Reconstruction
Estimated to start Mid June 2018
Estimated to end Early August 2018
Approx. % completed 60
Consultant WSP Canada Inc.
Contractor Asphaltec Paving Ltd.
Coniston St/Lyndale Dr - Lloyd St/Gauvin St   View Map
Facility type Alley
Type of work Reconstruction
Estimated to start Mid June 2018
Estimated to end Early August 2018
Approx. % completed 60
Consultant WSP Canada Inc.
Contractor Asphaltec Paving Ltd.
Coniston St/Lyndale Dr - Monck Av/Claremont Av   View Map
Facility type Alley
Type of work Reconstruction
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Consultant WSP Canada Inc.
Corydon Av/Shaftesbury Bv   View Map
Facility type Signal
Type of work Signal Improvements
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Cottonwood Rd - Lagimodiere Bv/Monaco By   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Consultant Morrison Hershfield Limited
Contractor Bituminex Paving Ltd
Creek Bend Rd/Sioux Rd W   View Map
Facility type Signal
Type of work Signal Improvements
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Culross By - Clouston Dr/Clouston Dr   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Mid May 2018
Estimated to end Early July 2018
Approx. % completed 95
Consultant Morrison Hershfield Limited
Dalhousie Dr/Silverstone Av   View Map
Facility type Signal
Type of work Signal Improvements
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Dartmouth Dr - Pembina Hw / 150m West of Snow St   View Map
Facility type Sidewalk
Type of work New - Sidewalk Construction
Estimated to start Late July 2018
Estimated to end Mid August 2018
Approx. % completed Planned
Consultant City Of Winnipeg - Engineering Division
Darwin St- Riel Av/Riverbend Av   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed 5
Consultant WSP Canada Inc.
Contractor J.C. Paving Ltd.
De Baets St - Paquin Rd/Beghin Av   View Map
Facility type Street
Type of work Reconstruction
Estimated to start Early August 2017
Estimated to end Early November 2017
Approx. % completed Complete
Consultant KGS Group Limited
Contractor Bayview Construction Ltd
De La Seigneurie Bv - Pauline Boutal Cr/Lessard Pl   View Map
Facility type Street
Type of work TBO
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Consultant WSP Canada Inc.
De Vries Av - McIvor Av/Springfield Rd   View Map
Facility type Street
Type of work Reconstruction
Estimated to start Early July 2018
Estimated to end To Be Determined
Approx. % completed 20
Consultant WSP Canada Inc.
Deer Run Dr - Lindenwood Dr W/Tipton Ct   View Map
Facility type Street
Type of work TBO
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Consultant WSP Canada Inc.
Des Meurons St - Vivian Av/Regal Av   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Late July 2017
Estimated to end Spring 2018
Approx. % completed 95
Consultant AECOM Canada Ltd
Contractor J.C. Paving Ltd.
Dominion St - Notre Dame Av/Yarwood Av   View Map
Facility type Street
Type of work Reconstruction
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Pre-Construction
Consultant Morrison Hershfield Limited
Contractor Bayview Construction Ltd
Donald St - Portage Av/Notre Dame Av   View Map
Facility type Street
Type of work Reconstruction
Estimated to start Mid May 2018
Estimated to end Late June 2018
Approx. % completed 85
Consultant AECOM Canada Ltd
Contractor Borland Construction Inc.
Additional information Click here
Donnelly St- Waller Av/Clarence Av   View Map
Facility type Street
Type of work Reconstruction
Estimated to start Early July 2018
Estimated to end Mid September 2018
Approx. % completed Planned
Consultant Morrison Hershfield Limited
Contractor Maple Leaf Construction Ltd.
Drake Bv - Elizabeth Rd/Autumnwood Dr   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start To be determined
Estimated to end To be determined
Approx. % completed 0
Consultant AECOM Canada Ltd
Contractor J.C. Paving Ltd.
Dublin Avenue Bridge Over Omand's Creek   View Map
Dugald Rd/396m East Of Plessis Rd   View Map
Facility type Signal
Type of work Signal Improvements
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Dugald Rd/Mazenod Rd   View Map
Facility type Signal
Type of work Signal Improvements
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Dundurn Pl/Wolseley Av-Maryland St/Walnut St   View Map
Facility type Alley
Type of work Reconstruction
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Pre-Construction
Consultant WSP Canada Inc.
Contractor J.C. Paving Ltd
Eastway - Empress St E/Empress St   View Map
Facility type Street
Type of work Mill and Fill
Estimated to start Early August 2018
Estimated to end Mid October 2018
Approx. % completed Planned
Consultant Morrison Hershfield Limited
Contractor Borland Construction Inc.
Additional information Click here
Edison Av- Raleigh St/De Graff Pl   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Consultant WSP Canada Inc.
Edmonton St- Backlane South of Broadway/Assiniboine Av   View Map
Facility type Sidewalk
Type of work Reconstruction
Estimated to start Late May 2018
Estimated to end Mid June 2018
Approx. % completed Planned
Consultant City Of Winnipeg - Engineering Division
Eglinton Cr - Scurfield Bv/Pincarrow Rd   View Map
Facility type Street
Type of work TBO
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Consultant City Of Winnipeg - Streets Maintenance Division
Contractor City Of Winnipeg - Centralized Services
Elizabeth Rd/95m East of Archibald St   View Map
Facility type Signal
Type of work Signal Improvements
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Ellice Av - Arlington St/Dominion St   View Map
Facility type Street
Type of work Reconstruction
Estimated to start Late May 2018
Estimated to end Early July 2018
Approx. % completed 70
Consultant Stantec Consulting Ltd.
Contractor Darco Enterprises Ltd.
Ellice Av - Dominion St/Erin St   View Map
Facility type Street
Type of work Reconstruction
Estimated to start Early August 2017
Estimated to end Late June 2018
Approx. % completed 95
Consultant Stantec Consulting Ltd.
Contractor Darco Enterprises Ltd.
Ellice Av/Hargrave St   View Map
Facility type Signal
Type of work Signal Improvements
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Empress St - Jack Blick Av/Portage Av   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Early August 2018
Estimated to end Mid October 2018
Approx. % completed Planned
Consultant Morrison Hershfield Limited
Contractor Borland Construction Inc.
Additional information Click here
Empress St E - Portage Av/Westway   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Early August 2018
Estimated to end Mid October 2018
Approx. % completed Planned
Consultant Morrison Hershfield Limited
Contractor Borland Construction Inc.
Additional information Click here
Empress St/Eastway   View Map
Facility type Signal
Type of work Signal Improvements
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Empress St/Westway   View Map
Facility type Signal
Type of work Signal Improvements
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Erin St/Clifton St - Ellice Av/St Matthews Av   View Map
Facility type Alley
Type of work Reconstruction
Estimated to start Mid May 2018
Estimated to end Late May 2018
Approx. % completed Complete
Consultant WSP Canada Inc.
Contractor J.C. Paving Ltd.
Fawn Pl- Woodstock Ln/Whitetail Dr   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Pre-Construction
Consultant AECOM Canada Ltd
Fermor Av - St Annes Rd/Archibald St   View Map
Facility type Street
Type of work Reconstruction
Estimated to start Early May 2018
Estimated to end Late October 2019
Approx. % completed 20
Consultant Dillon Consulting Limited
Contractor MD Steele
Fermor Av at Seine River Crossing   View Map
Facility type Bridge
Type of work Bridge - Culvert Installation
Estimated to start Early June 2018
Estimated to end To Be Determined
Approx. % completed 20
Consultant Dillon Consulting Limited
Contractor MD Steele
Additional information Click here
Fermor Av/1560m East of St Annes Rd   View Map
Facility type Signal
Type of work Signal Improvements
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Fermor Av/St Annes Rd   View Map
Facility type Signal
Type of work Signal Improvements
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Fermor Ave - Lagimodiere Bv/Plessis Rd   View Map
Facility type Street
Type of work Reconstruction
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Ferry Rd/McDermot Ave   View Map
Facility type Signal
Type of work Signal Improvements
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Ferry Rd/St Matthews Av   View Map
Facility type Signal
Type of work Signal Improvements
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Fidler Av - Mount Royal Rd/Mount Royal Rd   View Map
Facility type Street
Type of work Reconstruction
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed 10
Consultant AECOM Canada Ltd
Contractor Borland Construction Inc.
Fife St - College Av/Burrows Av   View Map
Facility type Street
Type of work Reconstruction
Estimated to start Mid July 2018
Estimated to end Late September 2018
Approx. % completed Pre-Construction
Consultant City Of Winnipeg - Engineering Division
Contractor Darco Enterprises Ltd.
Fife St - Inkster Bv/College Av   View Map
Facility type Street
Type of work Reconstruction
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Consultant AECOM Canada Ltd
Contractor Nelson River Construction Inc.
Fort St/York Av   View Map
Facility type Signal
Type of work Signal Improvements
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Furby St- William Av/Bannatyne Av   View Map
Facility type Sidewalk
Type of work Reconstruction
Estimated to start Early July 2018
Estimated to end Late July 2018
Approx. % completed 40
Consultant City Of Winnipeg - Engineering Division
Contractor Wintec Building Service Inc.
Furby St- William Av/McDermot Av   View Map
Facility type Sidewalk
Type of work Reconstruction
Estimated to start Early July 2018
Estimated to end Late July 2018
Approx. % completed 40
Consultant City Of Winnipeg - Engineering Division
Contractor Wintec Building Service Inc.
Gagnon St- Oxbow Bend Rd/Augier Av   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Consultant AECOM Canada Ltd
Garden Grove Dr - Fairgrove By/Burrows Av   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Mid May 2018
Estimated to end Early July 2018
Approx. % completed 95
Consultant City Of Winnipeg - Engineering Division
Contractor Darco Enterprises Ltd.
Garfield St N - Sargent Av/Ellice Av   View Map
Facility type Sidewalk
Type of work Reconstruction
Estimated to start Early June 2018
Estimated to end Late June 2018
Approx. % completed 95
Consultant City Of Winnipeg - Engineering Division
Contractor Wintec Building Service Inc.
Garry St - Broadway/York Av   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start To Be Determined
Estimated to end Mid October 2018
Approx. % completed Planned
Consultant AECOM Canada Ltd
Contractor J.C. Paving Ltd.
Garry St - Notre Dame Av/Assiniboine   View Map
Facility type Street
Type of work Reconstruction
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed 50
Consultant AECOM Canada Ltd
Contractor J.C. Paving Ltd.
Garry St - Notre Dame Av/Assiniboine   View Map
Facility type Street
Type of work Mill and Fill
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed 50
Consultant AECOM Canada Ltd
Contractor J.C. Paving Ltd.
Gateway Rd- Headmaster Rw / Bonner Av   View Map
Facility type Sidewalk
Type of work New - Sidewalk Construction
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Consultant City Of Winnipeg - Engineering Division
Glastonbury Bv - Lancaster Bv/Keswick Av   View Map
Facility type Street
Type of work TBO
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Pre-Construction
Consultant WSP Canada Inc.
Granville St - Rover Av/Euclid Av   View Map
Facility type Sidewalk
Type of work Reconstruction
Estimated to start Mid July 2018
Estimated to end Early August 2018
Approx. % completed Planned
Consultant City Of Winnipeg - Engineering Division
Contractor Wintec Building Service Inc.
Greene Av/Linden Av - Woodvale St/Kildonan Dr   View Map
Facility type Alley
Type of work Reconstruction
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Consultant WSP Canada Inc.
Haig Av- Egerton Rd/Des Meurons St   View Map
Facility type Street
Type of work Reconstruction
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Consultant WSP Canada Inc.
Contractor J.C. Paving Ltd.
Haresford Cr- Hawkins Cr/Novavista Dr   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Consultant WSP Canada Inc.
Contractor J.C. Paving Ltd.
Hargrave St/Bannatyne Av   View Map
Facility type Signal
Type of work Signal Improvements
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Hargrave St/McDermot Av   View Map
Facility type Signal
Type of work Signal Improvements
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Harkness St/Stradbrook Av   View Map
Facility type Signal
Type of work Signal Improvements
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Hatcher Rd - Bournais Dr/Rougeau Av   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Mid May 2018
Estimated to end To Be Determined
Approx. % completed 40
Consultant Morrison Hershfield Limited
Henderson Hw/Larsen Av   View Map
Facility type Signal
Type of work Signal Improvements
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Henderson Hw/McLeod Av   View Map
Facility type Signal
Type of work Signal Improvements
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Henlow By - Dovercourt Dr/Fultz Bv   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Mid August 2018
Estimated to end Early November 2018
Approx. % completed Planned
Consultant WSP Canada Inc.
Henlow By - Scurfield Bv/Dovercourt Dr   View Map
Facility type Street
Type of work Reconstruction
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Consultant WSP Canada Inc.
Higgins Av - Henry Av/Princess St   View Map
Facility type Street
Type of work Reconstruction
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Consultant WSP Canada Inc.
Highfield St/Coniston St - Chandos Av/Crawford Av   View Map
Facility type Alley
Type of work Reconstruction
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Consultant WSP Canada Inc.
Highfield St/Coniston St - Ferndale Av/Lawndale Av   View Map
Facility type Alley
Type of work Reconstruction
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed 0
Consultant WSP Canada Inc.
Contractor Asphaltec Paving Ltd.
Highgate Cr - Alburg Dr/Longford Av   View Map
Facility type Street
Type of work TBO
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Consultant WSP Canada Inc.
Homewood Dr - Knightsbridge Dr/Sterling Av   View Map
Facility type Street
Type of work TBO
Estimated to start To Be Determined
Estimated to end Mid July 2018
Approx. % completed Complete
Consultant City Of Winnipeg - Streets Maintenance Division
Contractor City Of Winnipeg - Centralized Services
Howden Rd - Harper Av/Betournay St   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Consultant Morrison Hershfield Limited
Contractor Bituminex Paving Ltd
Hutchings St - Inkster Bv/Sheppard St   View Map
Facility type Sidewalk
Type of work Rehabilitation
Estimated to start Early July 2018
Estimated to end To Be Determined
Approx. % completed 10
Consultant AECOM Canada Ltd
Contractor Nelson River Construction Inc.
Hutchings St - Inkster Bv/Sheppard St   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Early July 2018
Estimated to end To Be Determined
Approx. % completed 10
Consultant AECOM Canada Ltd
Contractor Nelson River Construction Inc.
Inkster Bv/Fife St   View Map
Facility type Signal
Type of work Signal Improvements
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Inkster Bv/McGregor St   View Map
Facility type Signal
Type of work Signal Improvements
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Isabel St/Bannatyne Av   View Map
Facility type Signal
Type of work Signal Improvements
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Isabel St/Ross Av   View Map
Facility type Signal
Type of work Signal Improvements
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Island Shore Bv - De La Seigneurie Bv/Leger Cr   View Map
Facility type Street
Type of work TBO
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Consultant WSP Canada Inc.
James Av - Lily St/Waterfront Dr   View Map
Facility type Street
Type of work Reconstruction
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Consultant WSP Canada Inc.
Jefferson Av - 65m West of Watson St   View Map
Facility type Signal
Type of work Signal Improvements
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Jefferson Av/McPhillips St   View Map
Facility type Signal
Type of work Signal Improvements
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Jefferson Av/Perth Av - Powers St/Andrews St   View Map
Facility type Alley
Type of work Reconstruction
Estimated to start Mid May 2018
Estimated to end Early June 2018
Approx. % completed Complete
Consultant WSP Canada Inc.
Contractor Bituminex Paving Ltd
Johnson Av W/Levis St   View Map
Facility type Signal
Type of work Signal Improvements
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Jones St - Belmont Av/Hartford Av   View Map
Facility type Street
Type of work Reconstruction
Estimated to start Early July 2018
Estimated to end To Be Determined
Approx. % completed 15
Consultant Morrison Hershfield Limited
Contractor Bayview Construction Ltd
Jones St - Smithfield Av / McAdam Av   View Map
Facility type Sidewalk
Type of work New - Sidewalk Construction
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Consultant City Of Winnipeg - Engineering Division
Keewatin St/Church Av   View Map
Facility type Signal
Type of work Signal Improvements
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Keewatin St/Sante Fe Dr   View Map
Facility type Signal
Type of work Signal Improvements
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Kennedy St- Graham Av/St Mary Av   View Map
Facility type Sidewalk
Type of work Reconstruction
Estimated to start Early July 2018
Estimated to end Early August 2018
Approx. % completed Planned
Consultant City Of Winnipeg - Engineering Division
Kennedy St- Graham Av/St Mary Av   View Map
Facility type Sidewalk
Type of work Reconstruction
Estimated to start Early July 2018
Estimated to end Early August 2018
Approx. % completed Planned
Consultant City Of Winnipeg - Engineering Division
Kennington By - Novavista Dr/Novavista Dr   View Map
Facility type Street
Type of work TBO
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Consultant WSP Canada Inc.
Kernaghan Av - Hoka St/Plessis Rd   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Mid May 2018
Estimated to end To Be Determined
Approx. % completed 40
Consultant Morrison Hershfield Limited
Kilbride Av - Scotia St/Main St   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Early July 2018
Estimated to end To Be Determined
Approx. % completed 5
Consultant Morrison Hershfield Limited
Contractor Bayview Construction Ltd
Killarney Av- Caledon Rd/Pembina Hw   View Map
Facility type Street
Type of work Reconstruction
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Consultant Morrison Hershfield Limited
Contractor Maple Leaf Construction Ltd.
King Edward St/Notre Dame Av   View Map
Facility type Signal
Type of work Signal Improvements
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
King St/Alexander Av   View Map
Facility type Signal
Type of work Signal Improvements
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Knightsbridge Dr- Ashworth St/Meadowood Dr   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Consultant WSP Canada Inc.
Contractor J.C. Paving Ltd.
La Fleche St/Nadeau St - Dumoulin St/Provencher Bv   View Map
Facility type Alley
Type of work Reconstruction
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Consultant WSP Canada Inc.
Lagimodiere Bv and Sage Creek Bv Intersection   View Map
Facility type Street
Type of work Intersection Improvement
Estimated to start Mid September 2017
Estimated to end Mid October 2017
Approx. % completed 95
Consultant Stantec Consulting Ltd.
Contractor Bituminex Paving Ltd
Lagimodiere Bv/Headmaster Rw   View Map
Facility type Signal
Type of work Signal Improvements
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Lake Ridge Rd - Harvlong Av/Lumsden Av   View Map
Facility type Sidewalk
Type of work Reconstruction
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Consultant City Of Winnipeg - Engineering Division
Lanark St - Grosvenor Av/Corydon Av   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Consultant Morrison Hershfield Limited
Contractor Maple Leaf Construction Ltd.
Langside St - Ellice Av/Portage Av   View Map
Facility type Street
Type of work TBO
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Pre-Construction
Consultant WSP Canada Inc.
Larsen Av - Brazier St/Henderson Hw   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Pre-Construction
Consultant WSP Canada Inc.
Lee Bv - Barnes St/Waverley St   View Map
Facility type Sidewalk
Type of work New Sidewalk
Estimated to start Mid May, 2018
Estimated to end Late June, 2018
Consultant Barnes and Duncan
Contractor Bayview Construction Ltd
Leila Av - 60m West of Simkin Dr   View Map
Facility type Signal
Type of work Signal Improvements
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Lewis St/Clarke St - Stradbrook Av/River Av   View Map
Facility type Alley
Type of work Reconstruction
Estimated to start Mid May 2018
Estimated to end Late May 2018
Approx. % completed Complete
Consultant WSP Canada Inc.
Contractor Bituminex Paving Ltd
Linwood St - Bruce Av/Portage Av   View Map
Facility type Sidewalk
Type of work Reconstruction
Estimated to start Early August 2017
Estimated to end Spring 2018
Approx. % completed Complete
Consultant City Of Winnipeg - Engineering Division
Contractor Wintec Building Services Inc.
Lipton St/Ingersoll St - Notre Dame Av/Yarwood Av   View Map
Facility type Alley
Type of work Reconstruction
Estimated to start Mid May 2018
Estimated to end Late May 2018
Approx. % completed Complete
Consultant WSP Canada Inc.
Contractor J.C. Paving Ltd.
Lodge Av - Moray St/Ronald St   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Consultant AECOM Canada Ltd
Contractor Borland Construction Inc.
Logan Av/Alexander Av-Ellen St/Laura St   View Map
Facility type Alley
Type of work Reconstruction
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Consultant WSP Canada Inc.
Contractor Bituminex Paving Ltd
Longford Av - Paddington Rd/Alburg Dr   View Map
Facility type Street
Type of work TBO
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Consultant WSP Canada Inc.
Loudoun Rd - Wilkes Av/Wyper Rd   View Map
Facility type Street
Type of work Reconstruction
Estimated to start Mid May 2018
Estimated to end Early September 2018
Approx. % completed 90
Consultant WSP Canada Inc.
Contractor Hugh Munro Construction
Main St/Alexander Av/Disraeli Fwy   View Map
Facility type Signal
Type of work Signal Improvements
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Main St/Logan Av   View Map
Facility type Signal
Type of work Signal Improvements
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Main St/Selkirk Av   View Map
Facility type Signal
Type of work Signal Improvements
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Maitland Dr - Paddington Rd/Charing Cross Cr   View Map
Facility type Street
Type of work TBO
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Consultant WSP Canada Inc.
Manitoba Av/McGregor St   View Map
Facility type Signal
Type of work Signal Improvements
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Mankato Cr - Herron Rd/Adsum Dr   View Map
Facility type Street
Type of work TBO
Estimated to start To Be Determined
Estimated to end Mid July 2018
Approx. % completed Complete
Consultant City Of Winnipeg - Streets Maintenance Division
Contractor City Of Winnipeg - Centralized Services
Manor House Ct - Mapleglen Dr/#81 Manor House Ct   View Map
Facility type Street
Type of work TBO
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Consultant WSP Canada Inc.
Manren Cr - Pipeline Rd/Blechner Dr   View Map
Facility type Street
Type of work TBO
Estimated to start To Be Determined
Estimated to end Mid July 2018
Approx. % completed Complete
Consultant City Of Winnipeg - Streets Maintenance Division
Contractor City Of Winnipeg - Centralized Services
Marion St/90m East of Archibald St   View Map
Facility type Signal
Type of work Signal Improvements
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Marion St/Tache Av   View Map
Facility type Signal
Type of work Signal Improvements
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Marrington Rd - Bairdmore Bv/Kirkbridge Dr   View Map
Facility type Street
Type of work TBO
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Consultant WSP Canada Inc.
Maryland St/Sherbrook St - North of 320 Sherbrook   View Map
Facility type Alley
Type of work Reconstruction
Estimated to start Mid May 2018
Estimated to end Mid June 2018
Approx. % completed 80
Consultant WSP Canada Inc.
Contractor J.C. Paving Ltd.
McBey Av - Summerlands Bv / Country Club Bv   View Map
Facility type Sidewalk
Type of work New - Sidewalk Construction
Estimated to start Late August 2018
Estimated to end Mid September 2018
Approx. % completed Planned
Consultant City Of Winnipeg - Engineering Division
McDermot Av/Ellen St   View Map
Facility type Signal
Type of work Signal Improvements
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
McDermot Av/Isabel St   View Map
Facility type Signal
Type of work Signal Improvements
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
McDermot Ave and Bannatyne Ave Adjustable Bike Lanes   View Map
Facility type Pedestrian / Cycling
Type of work New - Pedestrian / Cycling Construction
Estimated to start Early June 2018
Estimated to end Late August 2018
Consultant AECOM Canada Ltd
Contractor Darco Enterprises Ltd.
Additional information Click here
McGillivray Bv - Pembina Hw/Fennell St   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed 95
Consultant Morrison Hershfield Limited
Contractor J.C. Paving Ltd.
McGillivray Bv - Rapid Transit Corridor Overpass   View Map
Facility type Bridge
Type of work New - Rapid Transit Overpass Installation
Estimated to start Early May 2017
Estimated to end Late July 2018
Approx. % completed 10
Consultant Plenary Roads
Contractor PCL
Additional information Click here
McGillivray Bv/90m West of Pembina Hw   View Map
Facility type Signal
Type of work Signal Improvements
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
McGillivray Bv/Beaumont St   View Map
Facility type Signal
Type of work Signal Improvements
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
McGillivray Bv/Fennell St   View Map
Facility type Signal
Type of work Signal Improvements
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
McGregor St - Selkirk Av/Mountain Av   View Map
Facility type Street
Type of work Reconstruction
Estimated to start Early July 2018
Estimated to end To Be Determined
Approx. % completed 20
Consultant WSP Canada Inc.
McGregor St /Redwood Av   View Map
Facility type Signal
Type of work Signal Improvements
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
McGregor St/Burrows Av   View Map
Facility type Signal
Type of work Signal Improvements
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
McGregor St/Flora Av   View Map
Facility type Signal
Type of work Signal Improvements
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
McKenzie St - Back Lane/Inkster Bv   View Map
Facility type Sidewalk
Type of work Reconstruction
Estimated to start Mid July 2018
Estimated to end Early August 2018
Approx. % completed 5
Consultant City Of Winnipeg - Engineering Division
McPhillips St - Jarvis Av/Logan Av   View Map
Facility type Street
Type of work Reconstruction
Estimated to start Mid May 2018
Estimated to end Late October 2018
Approx. % completed 35
Consultant Dillon Consulting Limited
Contractor Borland Construction Inc.
McPhillips St - Logan Av/Jarvis Av   View Map
Facility type Street
Type of work Reconstruction
Estimated to start Mid May 2018
Estimated to end Late October 2018
Approx. % completed 35
Consultant Dillon Consulting Limited
Contractor Borland Construction Inc.
McPhillips St - Swailes Av/Leila Av   View Map
Facility type Street
Type of work Mill and Fill
Estimated to start Early June 2018
Estimated to end Early August 2018
Approx. % completed 75
Consultant City Of Winnipeg - Engineering Division
Contractor City Of Winnipeg - Centralized Services
McPhillips St/Burrows Av   View Map
Facility type Signal
Type of work Signal Improvements
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
McPhillips St/Leila Av   View Map
Facility type Signal
Type of work Signal Improvements
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
McPhillips St/Logan Av   View Map
Facility type Signal
Type of work Signal Improvements
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
McPhillips St/Machray Av   View Map
Facility type Signal
Type of work Signal Improvements
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Melrose Av W/Pandora Av W-Bond St/Winona St   View Map
Facility type Alley
Type of work Reconstruction
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Consultant WSP Canada Inc.
Contractor J.C. Paving Ltd
Memorial Bv - Portage Av/St Mary Av   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Pre-Construction
Consultant WSP Canada Inc.
Memorial Bv - Portage Av/St Mary Av   View Map
Facility type Street
Type of work Mill and Fill
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Pre-Construction
Consultant WSP Canada Inc.
Memorial Bv - York Av/Broadway   View Map
Facility type Pedestrian / Cycling
Type of work New - Pedestrian / Cycling Construction
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Consultant WSP Canada Inc.
Memorial Bv - York Av/St Mary Av   View Map
Facility type Street
Type of work Reconstruction
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Pre-Construction
Consultant WSP Canada Inc.
Merriwood Av - Sinclair St/Airlies St   View Map
Facility type Sidewalk
Type of work Reconstruction
Estimated to start Early August 2018
Estimated to end Late August 2018
Approx. % completed Planned
Consultant City Of Winnipeg - Engineering Division
Contractor Wintec Building Service Inc.
Messier St/90m East of Archibald St   View Map
Facility type Signal
Type of work Signal Improvements
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Minaki By - Vermillion Rd/Vermillion Rd   View Map
Facility type Street
Type of work TBO
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Consultant WSP Canada Inc.
Molson St - Nottingham Av/Union Av E   View Map
Facility type Street
Type of work Reconstruction
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Pre-Construction
Consultant WSP Canada Inc.
Moray St - Saulteaux Cr/Moray St   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Late May 2018
Estimated to end To Be Determined
Approx. % completed 50
Consultant AECOM Canada Ltd
Contractor Nelson River Construction Inc.
Moray St - Saulteaux Cr/Moray St   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Late May 2018
Estimated to end To Be Determined
Approx. % completed 50
Consultant AECOM Canada Ltd
Contractor Nelson River Construction Inc.
Morpeth Bv - North End/Taylor Av   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Pre-Construction
Consultant AECOM Canada Ltd
Murray Park Rd / Moray St - Cree Cr/Yellow Ribbon Trail   View Map
Facility type Pedestrian / Cycling
Type of work New Facility
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Consultant AECOM Canada Ltd
Contractor Nelson River Construction Inc.
Mutchmor Cs- Tu Pelo Av/Tu Pelo Av   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Pre-Construction
Consultant WSP Canada Inc.
Ness Av- Muriel St/Cavalier Dr   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed 10
Consultant AECOM Canada Ltd
Contractor Borland Construction Inc.
Norlorne Dr - Betsworth Av/Betsworth Av   View Map
Facility type Street
Type of work TBO
Estimated to start Mid August 2018
Estimated to end Late August 2018
Approx. % completed 20
Consultant City Of Winnipeg - Streets Maintenance Division
Contractor City Of Winnipeg - Centralized Services
Notre Dame Av - Donald St/Adelaide St   View Map
Facility type Street
Type of work New Facility - Protected Bike Lane
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Consultant AECOM Canada Ltd
Contractor J.C. Paving Ltd.
Additional information Click here
Notre Dame Av - Portage Av/Princess St   View Map
Facility type Street
Type of work Reconstruction
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed 20
Consultant AECOM Canada Ltd
Contractor J.C. Paving Ltd.
Additional information Click here
Notre Dame Av/Arthur St/Garry St   View Map
Facility type Signal
Type of work Signal Improvements
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Notre Dame Av/King St   View Map
Facility type Signal
Type of work Signal Improvements
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Notre Dame Av/Princess St   View Map
Facility type Signal
Type of work Signal Improvements
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed 20
Notre Dame Av/Sherbrook St   View Map
Facility type Signal
Type of work Signal Improvements
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Notre Dame Av/Weston St   View Map
Facility type Signal
Type of work Signal Improvements
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Notre Dame St/Dumoulin St - Archibald St/La Fleche St   View Map
Facility type Alley
Type of work Reconstruction
Estimated to start Mid June 2018
Estimated to end Early August 2018
Approx. % completed 70
Consultant WSP Canada Inc.
Contractor Asphaltec Paving Ltd.
Ocean Ridge Dr - Laurel Ridge Dr/Dovercourt Dr   View Map
Facility type Street
Type of work TBO
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Consultant WSP Canada Inc.
Osborne St/Glasgow Av   View Map
Facility type Signal
Type of work Signal Improvements
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Oswald By - Haney St/East End   View Map
Facility type Street
Type of work TBO
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Pre-Construction
Consultant WSP Canada Inc.
Oxford St- Corydon Av/Fleet Av   View Map
Facility type Street
Type of work Reconstruction
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Consultant Morrison Hershfield Limited
Contractor Maple Leaf Construction Ltd.
Panet Rd/160m North of Mission St   View Map
Facility type Signal
Type of work Signal Improvements
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Panet Rd/Molson St   View Map
Facility type Signal
Type of work Signal Improvements
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Paquin Rd - De Baets St/Beghin Av   View Map
Facility type Street
Type of work Reconstruction
Estimated to start Early August 2017
Estimated to end Early November 2017
Approx. % completed Complete
Consultant KGS Group Limited
Contractor Bayview Construction Ltd
Parkville Dr/Arden Av-Dunkirk Dr/Pulberry St   View Map
Facility type Alley
Type of work Reconstruction
Estimated to start Late June 2018
Estimated to end Mid July 2018
Approx. % completed 50
Consultant WSP Canada Inc.
Contractor Bituminex Paving Ltd
Parkwater Cr - Meadow Lake Dr/Devonshire Dr   View Map
Facility type Street
Type of work TBO
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Complete
Consultant City Of Winnipeg - Streets Maintenance Division
Contractor City Of Winnipeg - Centralized Services
Partridge Av/Royal Av-Powers St/Andrews St   View Map
Facility type Alley
Type of work Reconstruction
Estimated to start Late May 2018
Estimated to end Mid July 2018
Approx. % completed 90
Consultant WSP Canada Inc.
Contractor J.C. Paving Ltd
Peguis St/200m South of Concordia Av E   View Map
Facility type Signal
Type of work Signal Improvements
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Pembina Hw - Cloutier Dr/Ducharme Av   View Map
Facility type Street
Type of work Reconstruction
Estimated to start Late May 2018
Estimated to end Mid July 2018
Approx. % completed 80
Consultant Dillon Consulting Limited
Contractor Maple Leaf Construction Ltd.
Pembina Hw - Grant Av/Osborne St   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Early July 2016
Estimated to end Spring 2018
Approx. % completed 90
Consultant WSP Canada Inc.
Contractor J.C. Paving Ltd.
Additional information Click here
Pembina Hw - Grant Av/Osborne St   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Early July 2016
Estimated to end Spring 2018
Approx. % completed 90
Consultant WSP Canada Inc.
Contractor J.C. Paving Ltd.
Additional information Click here
Pembina Hw - Rapid Transit Corridor Underpass   View Map
Facility type Bridge
Type of work New - Rapid Transit Underpass Installation
Estimated to start Early April 2017
Estimated to end Late November 2019
Approx. % completed 30
Consultant Plenary Roads
Contractor PCL
Additional information Click here
Pembina Hw/Bairdmore Bv/Dalhousie Dr   View Map
Facility type Signal
Type of work Signal Improvements
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Pembina Hw/Clarence Av   View Map
Facility type Signal
Type of work Signal Improvements
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Pembina Hw/Ducharme Av   View Map
Facility type Signal
Type of work Signal Improvements
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Pembina Hw/Grandmont Bv   View Map
Facility type Signal
Type of work Signal Improvements
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Pembina Hw/Southpark Dr   View Map
Facility type Signal
Type of work New - Rapid Transit Signal Installation
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Pembina Hw/Stafford St   View Map
Facility type Signal
Type of work Signal Improvements
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Peony Av - Verbena St/Viola St   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Early July 2018
Estimated to end To Be Determined
Approx. % completed Pre-Construction
Consultant City Of Winnipeg - Engineering Division
Contractor Darco Enterprises Ltd.
Pinetree Cr - Ferngrove Wk/Vince Leah Dr   View Map
Facility type Street
Type of work TBO
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Consultant WSP Canada Inc.
Plessis Rd/Devonshire Dr   View Map
Facility type Signal
Type of work Signal Improvements
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Portage Av/Carlton St   View Map
Facility type Signal
Type of work Signal Improvements
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Portage Av/Country Club Bv   View Map
Facility type Signal
Type of work Signal Improvements
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Portage Av/Main St   View Map
Facility type Signal
Type of work Signal Improvements
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Portage Av/Mount Royal Cr   View Map
Facility type Signal
Type of work Signal Improvements
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Portage Av/Whytewold Rd   View Map
Facility type Signal
Type of work Signal Improvements
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Preston Av/Westminster Av-Ethelbert St/Home St   View Map
Facility type Alley
Type of work Reconstruction
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Pre-Construction
Consultant WSP Canada Inc.
Contractor J.C. Paving Ltd.
Princess St - Higgins Av/William Av   View Map
Facility type Pedestrian / Cycling
Type of work New - Pedestrian / Cycling Construction
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Consultant Stantec Consulting Ltd.
Princess St - William Av/Notre Dame Av   View Map
Facility type Street
Type of work Mill and Fill
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Pre-Construction
Consultant AECOM Canada Ltd
Contractor J.C. Paving Ltd.
Additional information Click here
Princess St/Bannatyne Av   View Map
Facility type Signal
Type of work Signal Improvements
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Provencher Bv - Des Meurons St/Archibald St   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Mid September 2017
Estimated to end Early Summer 2018
Approx. % completed 95
Consultant Stantec Consulting Ltd.
Contractor Bituminex Paving Ltd
Queenston St- Grosvenor Av/Corydon Av   View Map
Facility type Street
Type of work Reconstruction
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Consultant Morrison Hershfield Limited
Contractor Maple Leaf Construction Ltd.
Rapid Transit Corridor - Main St/Jubilee Av   View Map
Facility type Street
Type of work Preservation
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Consultant Stantec Consulting Ltd.
Rapid Transit Corridor - Phase 2   View Map
Facility type Rapid Transit Corridor
Type of work New - Rapid Transit Corridor
Estimated to start Summer 2016
Estimated to end Spring 2020
Approx. % completed 10
Consultant Plenary Roads
Contractor PCL
Additional information Click here
Ravelston Av W - Plessis Rd/Chrislind St   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Mid May 2018
Estimated to end Early July 2018
Approx. % completed 95
Consultant Morrison Hershfield Limited
Ravenhurst St/170m North of Dugald Rd   View Map
Facility type Signal
Type of work Signal Improvements
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Regatta Rd - Sun Valley Dr/Sun Valley Dr   View Map
Facility type Street
Type of work TBO
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Consultant City Of Winnipeg - Streets Maintenance Division
Contractor City Of Winnipeg - Centralized Services
Reitta St- Henry Av/Logan Av   View Map
Facility type Street
Type of work TBO
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Complete
Consultant City Of Winnipeg - Streets Maintenance Division
Contractor City Of Winnipeg - Centralized Services
River Av - Donald St/Osborne St   View Map
Facility type Street
Type of work Preservation
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Consultant Stantec Consulting Ltd.
Roberts Cr - Agnes Arnold Pl/Jefferson Av   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Early July 2018
Estimated to end Late August 2018
Approx. % completed Pre-Construction
Consultant City Of Winnipeg - Engineering Division
Contractor Darco Enterprises Ltd.
Roblin Bv - Assiniboine Park Dr/Shaftesbury Bv   View Map
Facility type Street
Type of work Reconstruction
Estimated to start Mid May 2018
Estimated to end Mid October 2018
Approx. % completed 20
Consultant City Of Winnipeg - Engineering Division
Contractor Bituminex Paving Ltd
Roblin Bv - Chalfont Rd/Shaftesbury Bv   View Map
Facility type Street
Type of work Reconstruction
Estimated to start Late May 2018
Estimated to end To Be Determined
Approx. % completed 40
Consultant City Of Winnipeg - Engineering Division
Roblin Bv/247m East of Chalfont Rd   View Map
Facility type Signal
Type of work Signal Improvements
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Roblin Bv/Dale Bv/Barker Bv   View Map
Facility type Signal
Type of work Signal Improvements
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Roslyn Rd - Nassau St N/Roslyn Cr   View Map
Facility type Street
Type of work TBO
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Complete
Consultant City Of Winnipeg - Streets Maintenance Division
Contractor City Of Winnipeg - Centralized Services
Ross Av - Ellen St/Isabel St   View Map
Facility type Street
Type of work TBO
Estimated to start To Be Determined
Estimated to end Mid July 2018
Approx. % completed Complete
Consultant City Of Winnipeg - Streets Maintenance Division
Contractor City Of Winnipeg - Centralized Services
Ross Av- Paulin St/ Lane   View Map
Facility type Sidewalk
Type of work New - Sidewalk Construction
Estimated to start Early July 2018
Estimated to end Late July 2018
Approx. % completed 90
Consultant City Of Winnipeg - Engineering Division
Rue Des Trappistes at Westendorf Coulee Culvert Replacement and Road Reconstruction Rue Du Monastere to Pembina Hwy   View Map
Facility type Bridge
Type of work New - Bridge Culvert Installation
Estimated to start Late November 2017
Estimated to end Summer 2018
Approx. % completed 10
Rue Des Trappistes at Westendorf Coulee Culvert Replacement and Road Reconstruction Rue Du Monastere to Pembina Hwy   View Map
Facility type Street
Type of work Reconstruction
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed 95
Rupertsland Av- Powers St/McGregor St   View Map
Facility type Street
Type of work Reconstruction
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Consultant Morrison Hershfield Limited
Contractor Bayview Construction Ltd
Rushmore Rd - St Moritz Rd/Thurlby Rd   View Map
Facility type Street
Type of work TBO
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Consultant WSP Canada Inc.
Salter St - Inkster Bv/Cathedral Av   View Map
Facility type Street
Type of work Reconstruction
Estimated to start Early July 2017
Estimated to end Early Summer 2018
Approx. % completed Complete
Consultant Morrison Hershfield Limited
Contractor Borland Construction Inc.
Sandalwood Cr - Rivergrove Dr/Red River Bv   View Map
Facility type Street
Type of work TBO
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Consultant WSP Canada Inc.
Sara Av/Westminster Av-Langside St/Furby St   View Map
Facility type Alley
Type of work Reconstruction
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Pre-Construction
Consultant WSP Canada Inc.
Contractor J.C. Paving Ltd
Sargent Av/Langside St   View Map
Facility type Signal
Type of work Signal Improvements
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Sargent/Ellice Av-Arlington St/Alverstone St   View Map
Facility type Alley
Type of work Reconstruction
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Pre-Construction
Consultant WSP Canada Inc.
Contractor J.C. Paving Ltd.
Saskatchewan Av - 2450 Saskatchewan Av/Moray St   View Map
Facility type Street
Type of work Reconstruction
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Consultant AECOM Canada Ltd
Contractor Nelson River Construction Inc.
Saskatchewan Av - Moray St/Sturgeon Rd   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Consultant AECOM Canada Ltd
Contractor Nelson River Construction Inc.
Saskatchewan Av at Sturgeon Creek   View Map
Facility type Bridge
Type of work Bridge - Culvert Installation
Estimated to start Mid May 2018
Estimated to end Late October 2018
Approx. % completed 20
Consultant Tetra Tech
Contractor Graham Construction and Engineering Inc.
Saulteaux Cr - Moray St/Moray St   View Map
Facility type Street
Type of work Reconstruction
Estimated to start Late May 2018
Estimated to end To Be Determined
Approx. % completed 45
Consultant AECOM Canada Ltd
Contractor Nelson River Construction Inc.
Scurfield Park   View Map
Facility type Pedestrian / Cycling
Type of work Reconstruction
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Consultant City Of Winnipeg - Engineering Division
Selkirk Av - Austin St N/Main St   View Map
Facility type Sidewalk
Type of work Reconstruction
Estimated to start Late June 2018
Estimated to end Early July 2018
Approx. % completed 95
Consultant City Of Winnipeg - Engineering Division
Contractor Wintec Building Service Inc.
Semple Av/Kilbride Av-Main St/Aikins St   View Map
Facility type Alley
Type of work Reconstruction
Estimated to start Late May 2018
Estimated to end Mid July 2018
Approx. % completed 95
Consultant WSP Canada Inc.
Contractor J.C. Paving Ltd.
Sherbrook St - McDermot Av/Cumberland Av   View Map
Facility type Street
Type of work Mill and Fill
Estimated to start Early June 2017
Estimated to end Spring 2018
Approx. % completed 50
Consultant Stantec Consulting Ltd.
Contractor Darco Enterprises Ltd.
Sherbrook St/Broadway   View Map
Facility type Signal
Type of work Signal Improvements
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Sherburn St - Wellington Av/Sargent Av   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Pre-Construction
Consultant Morrison Hershfield Limited
Contractor Bayview Construction Ltd
Sherburn St/Garfield St N - Notre Dame Av/Grundy Av   View Map
Facility type Alley
Type of work Reconstruction
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Consultant WSP Canada Inc.
Shoreview By-Orchard Ln/Beaverhill Bv   View Map
Facility type Alley
Type of work Reconstruction
Estimated to start Early July 2018
Estimated to end Early August 2018
Approx. % completed 10
Consultant WSP Canada Inc.
Contractor Bituminex Paving Ltd
Somerville Av/Somerset Av - Riverside Dr/Point Rd   View Map
Facility type Alley
Type of work Reconstruction
Estimated to start Early June 2017
Estimated to end Spring 2018
Approx. % completed Complete
Consultant WSP Canada Inc.
Contractor Asphaltec Paving Ltd.
Southfields Dr - Highbury Rd/Burland Av   View Map
Facility type Street
Type of work TBO
Estimated to start To Be Determined
Estimated to end Mid July 2018
Approx. % completed Complete
Consultant City Of Winnipeg - Streets Maintenance Division
Contractor City Of Winnipeg - Centralized Services
Speers Rd - Cottonwood Rd/Crestwood Cr   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Late August 2017
Estimated to end Late June 2018
Approx. % completed 95
Consultant AECOM Canada Ltd
Contractor J.C. Paving Ltd.
Spence St - Cumberland Av/Sargent Av   View Map
Facility type Street
Type of work Reconstruction
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Pre-Construction
Consultant Morrison Hershfield Limited
Contractor Bayview Construction Ltd
St Cross St - Polson Av/Atlantic Av   View Map
Facility type Street
Type of work TBO
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Consultant WSP Canada Inc.
St James St - 190m North of Ellice Av/Sargent Av   View Map
Facility type Street
Type of work Reconstruction
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
St Mary Av - Vaughan St/Memorial Bv   View Map
Facility type Sidewalk
Type of work Reconstruction
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Consultant City Of Winnipeg - Engineering Division
St Marys Rd - 115m North of Riel Av   View Map
Facility type Signal
Type of work Signal Improvements
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
St Marys Rd/Vivian Av   View Map
Facility type Signal
Type of work Signal Improvements
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
St Matthews Av - Century St/Berry St   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Late August 2017
Estimated to end Early June 2018
Approx. % completed 95
Consultant KGS Group Limited
Contractor Bayview Construction Ltd
St Matthews Av - Ferry Rd/Berry St   View Map
Facility type Street
Type of work Reconstruction
Estimated to start Late May 2018
Estimated to end Mid July 2018
Approx. % completed 85
Consultant KGS Group Limited
Contractor Bayview Construction Ltd
St Matthews Av/Valour Rd   View Map
Facility type Signal
Type of work Signal Improvements
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
St. Vital Trail - St Marys Rd/Charing Cross Cr/Paddington Rd   View Map
Facility type Pedestrian / Cycling
Type of work Reconstruction
Estimated to start To Be Determined
Estimated to end To Be Determined
Consultant City Of Winnipeg - Engineering Division
Sterling Lyon Pw - Wilkes Av/Kenaston Bv   View Map
Facility type Street
Type of work Preservation
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Consultant Stantec Consulting Ltd.
Sturgeon Rd/Saskatchewan Av   View Map
Facility type Signal
Type of work Signal Improvements
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Swindon Wy - Portsmouth Bv/Park Bv E   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Pre-Construction
Consultant AECOM Canada Ltd
Tache Av - St Marys Rd/Lyndale Dr   View Map
Facility type Street
Type of work Reconstruction
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Consultant Morrison Hershfield Limited
Contractor Bituminex Paving Ltd
Talbot Av/Brazier St   View Map
Facility type Signal
Type of work Signal Improvements
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Taylor Av - Guelph St/Nathaniel St   View Map
Facility type Sidewalk
Type of work Reconstruction
Estimated to start Mid May 2018
Estimated to end Mid June 2018
Approx. % completed Planned
Consultant City Of Winnipeg - Engineering Division
Taylor Av/Harrow St   View Map
Facility type Signal
Type of work Signal Improvements
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Thatcher Dr- North End/University Cr   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Early July 2018
Estimated to end Mid September 2018
Approx. % completed Planned
Consultant Morrison Hershfield Limited
Contractor Maple Leaf Construction Ltd.
Transcona Trail - Regent Ave W/Panet Rd   View Map
Facility type Pedestrian / Cycling
Type of work New - Pedestrian / Cycling Construction
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Pre-Construction
Consultant Stantec Consulting Ltd.
Contractor Darco Enterprises Ltd.
Transitway - Parker Av/Hurst Wy/Georgina St   View Map
Facility type Signal
Type of work New - Rapid Transit Signal Installation
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Transitway/Chancellor Dr   View Map
Facility type Signal
Type of work New - Rapid Transit Signal Installation
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Transitway/Chevrier Bv   View Map
Facility type Signal
Type of work New - Rapid Transit Signal Installation
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Transitway/Clarence Av   View Map
Facility type Signal
Type of work New - Rapid Transit Signal Installation
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Transitway/Markham Rd   View Map
Facility type Signal
Type of work New - Rapid Transit Signal Installation
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Transitway/University Cr   View Map
Facility type Signal
Type of work New - Rapid Transit Signal Installation
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Troy Av - McPhillips St/Fife St   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Early August 2018
Estimated to end Late September 2018
Approx. % completed Pre-Construction
Consultant City Of Winnipeg - Engineering Division
Contractor Darco Enterprises Ltd.
Truro Creek - Winchester St/Linwood St/Ness Av   View Map
Facility type Bridge
Type of work Bridge - Culvert Installation
Estimated to start Mid May 2018
Estimated to end Mid July 2018
Approx. % completed Planned
Consultant WSP Canada Inc.
Contractor J.C. Paving Ltd.
Additional information Click here
Tuxedo Av/Doncaster St   View Map
Facility type Signal
Type of work Signal Improvements
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Vaughan St - Ellice Av/Portage Av   View Map
Facility type Street
Type of work Preservation
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Consultant Stantec Consulting Ltd.
Walmer St/Kirkdale St - Lawndale Av/Birchdale Av   View Map
Facility type Alley
Type of work Reconstruction
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Consultant WSP Canada Inc.
Walnut St/Chestnut St - Westminster Av/Wolseley Av   View Map
Facility type Alley
Type of work Reconstruction
Estimated to start Mid May 2018
Estimated to end Mid June 2018
Approx. % completed 90
Consultant WSP Canada Inc.
Contractor Bituminex Paving Ltd
Wardlaw Av - Nassau St N/Daly St N   View Map
Facility type Street
Type of work TBO
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Pre-Construction
Consultant WSP Canada Inc.
Waterfront Dr - George Av/Lombard Av   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Consultant WSP Canada Inc.
Waterloo St/Ash St - Academy Rd/Kingsway   View Map
Facility type Alley
Type of work Reconstruction
Estimated to start Mid May 2018
Estimated to end Late May 2018
Approx. % completed Complete
Consultant WSP Canada Inc.
Contractor Bituminex Paving Ltd
Waverley St/Hurst Wy/Wilkes Av   View Map
Facility type Signal
Type of work Signal Improvements
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Waverley St/Taylor Av   View Map
Facility type Signal
Type of work Signal Improvements
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Waverley Underpass Project - Taylor Av / Waverley St / Wilkes Av / Grant Av   View Map
Facility type Street
Type of work Bridge - Roadway Reconstruction
Estimated to start Early May 2017
Estimated to end Mid October 2019
Approx. % completed 10
Consultant Dillon Consulting Limited
Contractor Maple Leaf Construction Ltd.
Additional information Click here
Waverley Underpass Project - Taylor Av / Waverley St / Wilkes Av / Grant Av   View Map
Facility type Bridge
Type of work New - Bridges Underpass Installation
Estimated to start Early May 2017
Estimated to end Mid October 2019
Approx. % completed 10
Consultant Dillon Consulting Limited
Contractor Maple Leaf Construction Ltd.
Additional information Click here
Wellington Av/Sargent Av-Banning St/Lipton St   View Map
Facility type Alley
Type of work Reconstruction
Estimated to start Late June 2018
Estimated to end Late July 2018
Approx. % completed 80
Consultant WSP Canada Inc.
Contractor J.C. Paving Ltd.
Wellington Av/Sargent Av-Toronto St/Beverley St   View Map
Facility type Alley
Type of work Reconstruction
Estimated to start Early July 2018
Estimated to end Mid August 2018
Approx. % completed 70
Consultant WSP Canada Inc.
Contractor J.C. Paving Ltd
Wellington Cr S - Academy Rd/Lanark St   View Map
Facility type Alley
Type of work Reconstruction
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Consultant WSP Canada Inc.
Contractor Bituminex Paving Ltd
Wellington Cr/Academy Rd-Elm St/Oak St   View Map
Facility type Alley
Type of work Reconstruction
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Consultant WSP Canada Inc.
Contractor Bituminex Paving Ltd
West Alexander Pedestrian and Cycling Corridor   View Map
Facility type Pedestrian / Cycling
Type of work New - Pedestrian / Cycling Construction
Estimated to start Mid August 2017
Estimated to end Late June 2018
Approx. % completed 50
Consultant Stantec Consulting Ltd.
Contractor Darco Enterprises Ltd.
Additional information Click here
West Alexander Pedestrian and Cycling Corridor   View Map
Facility type Pedestrian / Cycling
Type of work New - Pedestrian / Cycling Construction
Estimated to start Late August 2017
Estimated to end Spring 2018
Approx. % completed 85
Consultant Stantec Consulting Ltd.
Contractor Darco Enterprises Ltd.
Additional information Click here
Westbrook St - Pioneer Av/William Stephenson Wy   View Map
Facility type Street
Type of work Preservation
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Consultant Stantec Consulting Ltd.
Westminster Av/Wolseley Av-Evanson St/Wolseley Av   View Map
Facility type Alley
Type of work Reconstruction
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Pre-Construction
Consultant WSP Canada Inc.
Contractor J.C. Paving Ltd.
Westway - Empress St E/Empress St   View Map
Facility type Street
Type of work Mill and Fill
Estimated to start Early August 2018
Estimated to end Mid October 2018
Approx. % completed Planned
Consultant Morrison Hershfield Limited
Contractor Borland Construction Inc.
Additional information Click here
Whitegates Cr- Sansome Av/Barron Dr   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Consultant AECOM Canada Ltd
Contractor Borland Construction Inc.
Whitetail Dr- Chalfont Rd/Eldridge Av   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Pre-Construction
Consultant AECOM Canada Ltd
Whitley Dr- Ashworth St/Hawkins Cr   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Consultant WSP Canada Inc.
Contractor J.C. Paving Ltd.
Wilkes Av/Elmhurst Rd   View Map
Facility type Signal
Type of work Signal Improvements
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
William Av - Tecumseh St/Sherbrook St   View Map
Facility type Sidewalk
Type of work Reconstruction
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Consultant City Of Winnipeg - Engineering Division
William Av/Princess St   View Map
Facility type Signal
Type of work Signal Improvements
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
William Stephenson Wy - Israel Asper Wy/Provencher Bridge   View Map
Facility type Street
Type of work Preservation
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Consultant Stantec Consulting Ltd.
Winston Rd - Portage Av/Assiniboine Av   View Map
Facility type Street
Type of work TBO
Estimated to start Cancelled
Estimated to end Cancelled
Approx. % completed Cancelled
Consultant City Of Winnipeg - Streets Maintenance Division
Contractor City Of Winnipeg - Centralized Services
Woodhaven Bv- Sansome Av/Emo Av   View Map
Facility type Street
Type of work Reconstruction
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Consultant AECOM Canada Ltd
Contractor Borland Construction Inc.
Woodstock Ln- North End/Eldridge Av   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Pre-Construction
Consultant AECOM Canada Ltd
Yarwood Av/Wellington Av-Ingersoll St/Sherburn St   View Map
Facility type Alley
Type of work Reconstruction
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Pre-Construction
Consultant WSP Canada Inc.
Contractor J.C. Paving Ltd.
York Av - Edmonton St/Kennedy St   View Map
Facility type Sidewalk
Type of work Reconstruction
Estimated to start Late July 2018
Estimated to end Mid August 2018
Approx. % completed Planned
Consultant City Of Winnipeg - Engineering Division
York Av - Memorial Bv/Osborne St N   View Map
Facility type Street
Type of work Reconstruction
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Pre-Construction
Consultant WSP Canada Inc.
Young St - Cumberland Av/Sargent Av   View Map
Facility type Sidewalk
Type of work Reconstruction
Estimated to start Late June 2018
Estimated to end Early July 2018
Approx. % completed 95
Consultant City Of Winnipeg - Engineering Division
Contractor Wintec Building Service Inc.

Disclaimer and Indemnity:

The information on this web site is provided as a public service and should be used for general information purposes only. Although the information provided represents the planned capital work on city infrastructure for the current year, the City of Winnipeg cannot guarantee that it is accurate or current at all times. Although it is rare that projects are not finished within the stated timeframe, the City cannot guarantee that the work will be completed in all cases.

The information on this web site is subject to change without notice. Winnipeg.ca AND ITS AFFILIATES ARE NOT RESPONSIBLE IN ANY MANNER FOR DIRECT, INDIRECT, SPECIAL OR CONSEQUENTIAL DAMAGES HOWSOEVER CAUSED RESULTING FROM THE USE, MISUSE OR MISINTERPRETATION OF ANY CONTENT, PRODUCTS OR SERVICES PROVIDED BY THIS WEB SITE.

By using this site, you agree to indemnify, defend and hold harmless City of Winnipeg and its officials, officers, employees and authorized representatives from and against any liability, loss injury (including injuries resulting in death), demand, action, cost, expense, or claim of any kind, including but not limited to lawyer's fees, relating in any way to your use of the contents, or services provided by this web site.