Site Accessibility Information Access Key 1 to Skip to Top Navigation Access Key 2 to Skip to the Three One One link Access Key 3 to Skip to City of Winnipeg Main Menu Access Key 4 to Skip to Left Navigation Menu Access Key 5 to Skip to Content area Access Key 6 to Skip to Right Sidebar content area Access Key 7 to Skip to Footer Links
City of Winnipeg
|  Link to the City of Winnipeg French websiteFrançais  |
Public Works

Road Construction List

The roadway construction list provides project information in alphabetical order by street name. Project information is available by location in both map and list format. Please see the regional street lane closures page for information on current lane closures on major streets.

How to use the construction list

Click on the + beside the project name. A dropdown box will appear with these project details:

  1. type of infrastructure (street, alley, sidewalk, traffic signal, bridge project, pedestrian and cycling path),
  2. type of construction work (reconstruction, rehabilitation, mill & fill, thin bituminous overlay, improvements within the right-of-way)
  3. estimated to start,
  4. estimated to end,
  5. approximate percentage completed:
    • Pre-Construction – Construction phase has not started.
    • 0% – Construction contract is in place, but crews have not mobilized to the site.
    • 5% – Crews have mobilized to the site and construction has just begun.
    • 10% 90% – An approximation of progress; construction is well underway.
    • 95% – Main roadway construction is complete; travelling lanes are open/parking is restored/garbage pickup resumes (depending on the location); minor deficiencies and landscaping (seeding/sod) are likely outstanding.
    • COMPLETE – All construction components of the project are complete. Contractor may return for any follow up or warranty work in the next 1-2 years. Utilities (e.g. street lights) may or may not be complete. Construction may not be complete for other locations in the same contract.
  6. consultant information, and
  7. contractor information.

You can also view projects by street name using the Search box provided. Click "View Map" beside any project name to view in a map.

Note: As construction projects get underway this season the information about start dates and completion dates will be updated to reflect the actual project timeline.

A   B   C   D   E   F   G   H   I   J   K   L   M   N   O   P   Q   R   S   T   U   V   W   X   Y   Z


City of Winnipeg - Public Works Capital Projects
(Last updated on May 21, 2019 @ 8:00 PM)
 
 
View All on Map


800m East of Lagimodiere Bv/Fermor Av   View Map
Facility type Signal
Type of work Signal Improvements
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
932 Archibald St   View Map
Facility type Signal
Type of work Signal Improvements
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Academy Rd / Queenston St   View Map
Facility type Signal
Type of work Signal Improvements
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Agnes Arnold Pl - Leila Av/Roberts Cr   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Summer 2018
Estimated to end Spring 2019
Approx. % completed 95
Consultant City Of Winnipeg - Engineering Division
Contractor Darco Enterprises Ltd.
Aikins St - North End/Templeton Av   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Summer 2018
Estimated to end Spring 2019
Approx. % completed 95
Consultant WSP Canada Inc.
Contractor Darco Enterprises Ltd.
Alexander Ave / Disraeli Fwy / Main St   View Map
Facility type Signal
Type of work Signal Improvements
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Assiniboine Park Dr - Commissary Rd/Zoo Dr   View Map
Facility type Street
Type of work Mill and Fill
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Consultant City Of Winnipeg - Engineering Division
Assiniboine Park Dr - Commissary Rd/Zoo Dr   View Map
Facility type Street
Type of work Reconstruction
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Consultant City Of Winnipeg - Engineering Division
Bannerman Av - Airlies St/McPhillips St   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Summer 2018
Estimated to end Spring 2019
Approx. % completed 95
Consultant City Of Winnipeg - Engineering Division
Contractor Darco Enterprises Ltd.
Bayne Cr- London St/Tu Pelo Av   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Summer 2018
Estimated to end Spring 2019
Approx. % completed 95
Consultant WSP Canada Inc.
Contractor Darco Enterprises Ltd.
Beresford Av - Osborne St/Daly St S   View Map
Facility type Street
Type of work Reconstruction
Estimated to start Summer 2018
Estimated to end Spring 2019
Approx. % completed 95
Consultant WSP Canada Inc.
Contractor J.C. Paving Ltd.
Bishop Grandin Bv - Rapid Transit Corridor Overpass   View Map
Facility type Bridge
Type of work New - Rapid Transit Overpass Installation
Estimated to start February 2017
Estimated to end Spring 2020
Approx. % completed 30
Consultant Plenary Roads
Contractor PCL
Additional information Click here
Bishop Grandin Bv / Kenaston Bv   View Map
Facility type Signal
Type of work Signal Improvements
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Bishop Grandin Bv / St Marys Rd   View Map
Facility type Signal
Type of work Signal Improvements
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Brighton Ct/Kildare Av E-Southampton Pl/Wayoata St   View Map
Facility type Alley
Type of work Reconstruction
Estimated to start Summer 2018
Estimated to end Spring 2019
Approx. % completed 95
Consultant WSP Canada Inc.
Contractor J.C. Paving Ltd
Broadway - Sherbrook St/Portage Av   View Map
Facility type Street
Type of work Mill and Fill
Estimated to start Summer 2018
Estimated to end Spring 2019
Approx. % completed 95
Consultant Stantec Consulting Ltd.
Contractor Bituminex Paving Ltd
Broadway/Garry St   View Map
Facility type Signal
Type of work Signal Improvements
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Bronx Av - Grey St/Gateway Rd   View Map
Facility type Sidewalk
Type of work Reconstruction
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Consultant City Of Winnipeg - Engineering Division
Burrows Av / Keewatin St   View Map
Facility type Signal
Type of work Signal Improvements
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Cail By - Jefferson Av/Jefferson Av   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Summer 2018
Estimated to end Spring 2019
Approx. % completed 95
Consultant City Of Winnipeg - Engineering Division
Contractor Darco Enterprises Ltd.
Cavalier Dr / Portage Av   View Map
Facility type Signal
Type of work Signal Improvements
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Century St/St Matthews Av   View Map
Facility type Signal
Type of work Signal Improvements
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Century St/Wellington Av   View Map
Facility type Signal
Type of work Signal Improvements
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Chambers St - Logan Av/Alexander Av   View Map
Facility type Street
Type of work Reconstruction
Estimated to start Summer 2018
Estimated to end Spring 2019
Approx. % completed 95
Consultant City Of Winnipeg - Engineering Division
Contractor Darco Enterprises Ltd.
Chevrier Bv - Pembina Hw/Trottier By   View Map
Facility type Street
Type of work Reconstruction
Estimated to start Summer 2018
Estimated to end Spring 2019
Approx. % completed 95
Consultant WSP Canada Inc.
Contractor Bayview Construction Ltd
Chevrier Bv - Trottier By/Waverley St   View Map
Facility type Street
Type of work Mill and Fill - Pavement Widening
Estimated to start Summer 2018
Estimated to end Spring 2019
Approx. % completed 95
Consultant WSP Canada Inc.
Contractor Bayview Construction Ltd
Chief Peguis Greenway Extension   View Map
Facility type Pedestrian / Cycling
Type of work New - Pedestrian / Cycling Construction
Estimated to start Summer 2018
Estimated to end Spring 2020
Approx. % completed 90
Consultant WSP Canada Inc.
Contractor J.C. Paving Ltd.
Additional information Click here
Chief Peguis Tl/Gateway Rd   View Map
Facility type Signal
Type of work Signal Improvements
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Chief Peguis Tl/Henderson Hw   View Map
Facility type Signal
Type of work Signal Improvements
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Churchill Dr - Eccles St/Casey St   View Map
Facility type Street
Type of work Reconstruction
Estimated to start Summer 2018
Estimated to end Spring 2019
Approx. % completed 95
Consultant WSP Canada Inc.
Contractor J.C. Paving Ltd.
Colony St - Ellice Av / Portage Av   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Early June 2019
Estimated to end Late October 2019
Approx. % completed Pre-Construction
Consultant WSP Canada Inc.
Coniston St/Lyndale Dr - Claremont Av/Ferndale Av   View Map
Facility type Alley
Type of work Reconstruction
Estimated to start Early May 2019
Estimated to end Late June 2019
Approx. % completed Planned
Consultant WSP Canada Inc.
Contractor Asphaltec Paving Ltd.
Coniston St/Lyndale Dr - Monck Av/Claremont Av   View Map
Facility type Alley
Type of work Reconstruction
Estimated to start Early May 2019
Estimated to end Late June 2019
Approx. % completed Planned
Consultant WSP Canada Inc.
Contractor Asphaltec Paving Ltd.
Corydon Av - Borebank St/Brock St   View Map
Facility type Street
Type of work Reconstruction
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Consultant AECOM Canada Ltd
Corydon Av - Cordova St/Lanark St   View Map
Facility type Street
Type of work Reconstruction
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Consultant AECOM Canada Ltd
Corydon Av - Daly St N / Corydon Av   View Map
Facility type Sidewalk
Type of work Reconstruction
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Consultant City Of Winnipeg - Engineering Division
Corydon Av / Brock St   View Map
Facility type Signal
Type of work Signal Improvements
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Corydon Av / Harrow St   View Map
Facility type Signal
Type of work Signal Improvements
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Corydon Av/Conservatory Dr   View Map
Facility type Signal
Type of work Signal Improvements
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Corydon Av/Osborne St   View Map
Facility type Signal
Type of work Signal Improvements
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Corydon Av/Pembina Hw   View Map
Facility type Signal
Type of work Signal Improvements
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Dalhousie Dr/Silverstone Av   View Map
Facility type Signal
Type of work Signal Improvements
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Darwin St- Riel Av/Riverbend Av   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Summer 2018
Estimated to end Spring 2019
Approx. % completed 95
Consultant WSP Canada Inc.
Contractor J.C. Paving Ltd.
De Bourmont Av - Maginot St/Elizabeth Rd   View Map
Facility type Sidewalk
Type of work Reconstruction
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Consultant City Of Winnipeg - Engineering Division
De Vries Av - McIvor Av/Springfield Rd   View Map
Facility type Street
Type of work Reconstruction
Estimated to start Summer 2018
Estimated to end Spring 2019
Approx. % completed 95
Consultant WSP Canada Inc.
Contractor Darco Enterprises Ltd.
Des Meurons St - Vivian Av/Regal Av   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Summer 2018
Estimated to end Spring 2019
Approx. % completed 95
Consultant AECOM Canada Ltd
Contractor J.C. Paving Ltd.
Devonshire Dr/Plessis Rd   View Map
Facility type Signal
Type of work Signal Improvements
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Donald St - Portage Av/Notre Dame Av   View Map
Facility type Street
Type of work Reconstruction
Estimated to start Summer 2018
Estimated to end Spring 2019
Approx. % completed 95
Consultant AECOM Canada Ltd
Contractor Borland Construction Inc.
Additional information Click here
Drake Bv - Elizabeth Rd/Autumnwood Dr   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Summer 2018
Estimated to end Spring 2019
Approx. % completed 95
Consultant AECOM Canada Ltd
Contractor J.C. Paving Ltd.
Dublin Av - Midland St/St James St   View Map
Facility type Street
Type of work Reconstruction
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed 0
Consultant Stantec Consulting Ltd
Additional information Click here
Dublin Av / Border St   View Map
Facility type Signal
Type of work Signal Improvements
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Dublin Avenue Bridge Over Omand's Creek   View Map
Facility type Bridge
Estimated to start Summer 2018
Estimated to end Spring 2019
Approx. % completed 0
Consultant Stantec Consulting Ltd
Additional information Click here
Dugald Rd / Ravenhurst St   View Map
Facility type Signal
Type of work Signal Improvements
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Dugald Rd/Lagimodiere Bv   View Map
Facility type Signal
Type of work Signal Improvements
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Dundurn Pl/Wolseley Av-Maryland St/Walnut St   View Map
Facility type Alley
Type of work Reconstruction
Estimated to start Summer 2018
Estimated to end Spring 2019
Approx. % completed 95
Consultant WSP Canada Inc.
Contractor J.C. Paving Ltd
Ellice Av - Maryland St/Arlington St   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Mid June 2019
Estimated to end Late September 2019
Approx. % completed Planned
Consultant Dillon Consulting Limited
Ellice Av / Toronto St   View Map
Facility type Signal
Type of work Signal Improvements
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Ellice Av/Agnes St   View Map
Facility type Signal
Type of work Signal Improvements
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Ellice Av/Balmoral St/Colony St   View Map
Facility type Signal
Type of work Signal Improvements
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Ellice Av/Maryland St   View Map
Facility type Signal
Type of work Signal Improvements
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Empress St / Jack Blick Av   View Map
Facility type Signal
Type of work Signal Improvements
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Empress St E - Portage Av/Westway   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Summer 2018
Estimated to end Summer 2020
Approx. % completed 95
Consultant Morrison Hershfield Limited
Contractor Borland Construction Inc.
Additional information Click here
Empress St/Maroons Rd   View Map
Facility type Signal
Type of work Signal Improvements
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Fawn Pl- Woodstock Ln/Whitetail Dr   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Summer 2018
Estimated to end Spring 2019
Approx. % completed 95
Consultant AECOM Canada Ltd
Contractor Darco Enterprises Ltd.
Fermor Av - 500m West of Lagimodiere Bv / CN Overpass   View Map
Facility type Street
Type of work Reconstruction
Estimated to start Early June 2019
Estimated to end Late October 2020
Approx. % completed Planned
Consultant Morrison Hershfield Limited
Fermor Av at Seine River Crossing   View Map
Facility type Bridge
Type of work Bridge - Culvert Installation
Estimated to start Summer 2018
Estimated to end Summer 2019
Approx. % completed 45
Consultant Dillon Consulting Limited
Contractor MD Steele
Additional information Click here
Fermor Av/Archibald St/Royal Salinger Rd   View Map
Facility type Signal
Type of work Signal Improvements
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Fermor Avenue Bridge over the Seine River Rehabilitation and Roadworks from St. Anne's Road to Archibald Street   View Map
Facility type Street
Type of work Reconstruction
Estimated to start Spring 2018
Estimated to end Fall 2019
Approx. % completed 20
Consultant Dillon Consulting Limited
Contractor MD Steele
Fife St - College Av/Burrows Av   View Map
Facility type Street
Type of work Reconstruction
Estimated to start Summer 2018
Estimated to end Spring 2019
Approx. % completed 95
Consultant City Of Winnipeg - Engineering Division
Contractor Darco Enterprises Ltd.
Fife St - Inkster Bv/College Av   View Map
Facility type Street
Type of work Reconstruction
Estimated to start Mid May 2019
Estimated to end Late July 2019
Approx. % completed Planned
Consultant AECOM Canada Ltd
Contractor Nelson River Construction Inc.
Fife St - Inkster Bv/College Av   View Map
Facility type Sidewalk
Type of work New - Sidewalk Construction
Estimated to start Mid May 2019
Estimated to end Late July 2019
Approx. % completed Planned
Consultant AECOM Canada Ltd
Contractor Nelson River Construction Inc.
Fife St/ Church Av   View Map
Facility type Signal
Type of work Signal Improvements
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Fort St/York Av   View Map
Facility type Signal
Type of work Signal Improvements
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Gagnon St- Oxbow Bend Rd/Augier Av   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Summer 2018
Estimated to end Spring 2019
Approx. % completed 95
Consultant AECOM Canada Ltd
Contractor Darco Enterprises Ltd.
Garden Grove Dr - Fairgrove By/Burrows Av   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Summer 2018
Estimated to end Spring 2019
Approx. % completed 95
Consultant City Of Winnipeg - Engineering Division
Contractor Darco Enterprises Ltd.
Garry St - Broadway/Assiniboine   View Map
Facility type Street
Type of work Mill and Fill
Estimated to start Early May 2019
Estimated to end Late August 2019
Approx. % completed 0
Consultant AECOM Canada Ltd
Contractor J.C. Paving Ltd.
Garry St - Notre Dame Av/Portage Av   View Map
Facility type Street
Type of work Reconstruction
Estimated to start Summer 2018
Estimated to end Late August 2019
Approx. % completed 95
Consultant AECOM Canada Ltd
Contractor J.C. Paving Ltd.
Garry St - Portage Av/Broadway   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Early May 2019
Estimated to end Late August 2019
Approx. % completed 0
Consultant AECOM Canada Ltd
Contractor J.C. Paving Ltd.
Garry St / Graham Av   View Map
Facility type Signal
Type of work Signal Improvements
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Garry St / Portage Av   View Map
Facility type Signal
Type of work Signal Improvements
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Grant Av / Stafford St   View Map
Facility type Signal
Type of work Signal Improvements
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Grant Av/Kenaston Bv   View Map
Facility type Signal
Type of work Signal Improvements
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Greene Av/Linden Av - Woodvale St/Kildonan Dr   View Map
Facility type Alley
Type of work Reconstruction
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Consultant WSP Canada Inc.
Greenwood Av- Wyoming St/ #49 Greenwood Av   View Map
Facility type Sidewalk
Type of work Reconstruction
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Consultant City Of Winnipeg - Engineering Division
Haig Av- Egerton Rd/Des Meurons St   View Map
Facility type Street
Type of work Reconstruction
Estimated to start Fall 2018
Estimated to end Spring 2019
Approx. % completed 95
Consultant WSP Canada Inc.
Contractor J.C. Paving Ltd.
Haresford Cr- Hawkins Cr/Novavista Dr   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Fall 2018
Estimated to end Spring 2019
Approx. % completed 95
Consultant WSP Canada Inc.
Contractor J.C. Paving Ltd.
Harkness St/Stradbrook Av   View Map
Facility type Signal
Type of work Signal Improvements
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Henderson Hw/Larsen Av   View Map
Facility type Signal
Type of work Signal Improvements
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Henlow By - Dovercourt Dr/Fultz Bv   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Summer 2018
Estimated to end Spring 2019
Approx. % completed 95
Consultant WSP Canada Inc.
Contractor Bayview Construction Ltd
Henlow By - Scurfield Bv/Dovercourt Dr   View Map
Facility type Street
Type of work Reconstruction
Estimated to start Summer 2018
Estimated to end Spring 2019
Approx. % completed 95
Consultant WSP Canada Inc.
Contractor Bayview Construction Ltd
Higgins Av - Henry Av/Princess St   View Map
Facility type Street
Type of work Reconstruction
Estimated to start Mid May 2019
Estimated to end Late July 2019
Approx. % completed Planned
Consultant WSP Canada Inc.
Contractor Bayview Construction Ltd
Highfield St/Coniston St - Chandos Av/Crawford Av   View Map
Facility type Alley
Type of work Reconstruction
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Consultant WSP Canada Inc.
Hutchings St - Inkster Bv/Sheppard St   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Summer 2018
Estimated to end Summer 2019
Approx. % completed 75
Consultant AECOM Canada Ltd
Contractor Nelson River Construction Inc.
Inkster Bv - Fife St/Milner St   View Map
Facility type Street
Type of work Reconstruction
Estimated to start Early June 2019
Estimated to end Late September 2019
Approx. % completed Planned
Consultant Morrison Hershfield Limited
Inkster Bv/70m West of Lansdowne Av   View Map
Facility type Signal
Type of work Signal Improvements
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Inkster Bv/Fife St   View Map
Facility type Signal
Type of work Signal Improvements
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Inkster Bv/McPhillips St   View Map
Facility type Signal
Type of work Signal Improvements
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Jefferson Av/65m West of Watson St   View Map
Facility type Signal
Type of work Signal Improvements
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Jefferson Av/McPhillips St   View Map
Facility type Signal
Type of work Signal Improvements
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Jubilee Av/Pembina Hw   View Map
Facility type Signal
Type of work Signal Improvements
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Keewatin St - Inkster Bv/Burrows Av   View Map
Facility type Pedestrian / Cycling
Type of work New - Pedestrian / Cycling Construction
Estimated to start Summer 2018
Estimated to end Spring 2019
Approx. % completed 95
Consultant Stantec Consulting Ltd
Contractor Darco Enterprises Ltd.
Additional information Click here
Kenaston Bv - McGillivray Bv/Scurfield Bv   View Map
Facility type Street
Type of work Preservation
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
King St/Alexander Av   View Map
Facility type Signal
Type of work Signal Improvements
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Knightsbridge Dr- Ashworth St/Meadowood Dr   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Summer 2018
Estimated to end Spring 2019
Approx. % completed 95
Consultant WSP Canada Inc.
Contractor J.C. Paving Ltd.
Lagimodiere Bv - Dugald Rd/Regent Av W   View Map
Facility type Street
Type of work Mill and Fill
Estimated to start Summer 2018
Estimated to end Spring 2019
Approx. % completed 95
Consultant Stantec Consulting Ltd
Contractor Bituminex Paving Ltd
Lagimodiere Bv / Almey Av   View Map
Facility type Signal
Type of work Signal Improvements
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Lagimodiere Bv and Sage Creek Bv Intersection   View Map
Facility type Street
Type of work Intersection Improvement
Estimated to start Summer 2018
Estimated to end Spring 2019
Approx. % completed 95
Consultant Stantec Consulting Ltd.
Contractor Bituminex Paving Ltd
Lagimodiere Bv/Fermor Av   View Map
Facility type Signal
Type of work Signal Improvements
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Larsen Av - Brazier St/Henderson Hw   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Summer 2018
Estimated to end Spring 2019
Approx. % completed 95
Consultant WSP Canada Inc.
Contractor Darco Enterprises Ltd.
Lavalee Rd/St Annes Rd   View Map
Facility type Signal
Type of work Signal Improvements
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Leila Av/ 157m East of McPhillips St   View Map
Facility type Signal
Type of work Signal Improvements
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Leila Av/ 60m East of Simkin Dr   View Map
Facility type Signal
Type of work Signal Improvements
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Leila Av/Main St   View Map
Facility type Signal
Type of work Signal Improvements
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Logan Av/Keewatin St   View Map
Facility type Signal
Type of work Signal Improvements
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Logan Av/Princess St   View Map
Facility type Signal
Type of work Signal Improvements
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Lombard Av / Westbrook St   View Map
Facility type Signal
Type of work Signal Improvements
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
London St - Prince Rupert Av/Munroe Av   View Map
Facility type Sidewalk
Type of work Reconstruction
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Consultant City Of Winnipeg - Engineering Division
Loudoun Rd - Wilkes Av/Wyper Rd   View Map
Facility type Street
Type of work Reconstruction
Estimated to start Spring 2018
Estimated to end Late June 2019
Approx. % completed 95
Consultant WSP Canada Inc.
Contractor Hugh Munro Construction
Madeline St - Edward Av W/Harold Av W   View Map
Facility type Sidewalk
Type of work Reconstruction
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Consultant City Of Winnipeg - Engineering Division
Main St - McAdam Av/ Kildonan Pk Golf Cs.   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Late April 2019
Estimated to end Late October 2019
Approx. % completed Planned
Consultant Stantec Consulting Ltd
Main St/ McKay Dr   View Map
Facility type Signal
Type of work Signal Improvements
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Main St/ Smithfield Av   View Map
Facility type Signal
Type of work Signal Improvements
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Main St/Hartford Av   View Map
Facility type Signal
Type of work Signal Improvements
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Main St/Kingsbury Av   View Map
Facility type Signal
Type of work Signal Improvements
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Main St/Partridge Av   View Map
Facility type Signal
Type of work Signal Improvements
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Main St/Seven Oaks Av   View Map
Facility type Signal
Type of work Signal Improvements
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Marion St/Dawson Rd N   View Map
Facility type Signal
Type of work Signal Improvements
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Marion St/Lagimodiere Bv   View Map
Facility type Signal
Type of work Signal Improvements
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
McGillivray Bv - Rapid Transit Corridor Overpass   View Map
Facility type Bridge
Type of work New - Rapid Transit Overpass Installation
Estimated to start Spring 2017
Estimated to end Spring 2020
Approx. % completed 30
Consultant Plenary Roads
Contractor PCL
Additional information Click here
McGregor St - Selkirk Av/Mountain Av   View Map
Facility type Street
Type of work Reconstruction
Estimated to start Summer 2018
Estimated to end Spring 2019
Approx. % completed 95
Consultant KGS Group Limited
Contractor Bayview Construction Ltd
McIvor Av - Reiny Dr/Henderson Hw   View Map
Facility type Sidewalk
Type of work Reconstruction
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Consultant City Of Winnipeg - Engineering Division
McPhillips St - Jarvis Av/Logan Av   View Map
Facility type Street
Type of work Reconstruction
Estimated to start Mid May 2018
Estimated to end Mid June 2019
Approx. % completed 80
Consultant Dillon Consulting Limited
Contractor Borland Construction Inc.
McPhillips St - Logan Av/Jarvis Av   View Map
Facility type Street
Type of work Reconstruction
Estimated to start Mid May 2018
Estimated to end Mid June 2019
Approx. % completed 80
Consultant Dillon Consulting Limited
Contractor Borland Construction Inc.
McPhillips St / Kingsbury Av   View Map
Facility type Signal
Type of work Signal Improvements
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
McPhillips St/Burrows Av   View Map
Facility type Signal
Type of work Signal Improvements
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Melrose Av W/Pandora Av W-Bond St/Winona St   View Map
Facility type Alley
Type of work Reconstruction
Estimated to start Summer 2018
Estimated to end Spring 2019
Approx. % completed 95
Consultant WSP Canada Inc.
Contractor J.C. Paving Ltd
Memorial Bv - Portage Av/St Mary Av   View Map
Facility type Street
Type of work Mill and Fill
Estimated to start Early June 2019
Estimated to end Late October 2019
Approx. % completed Pre-Construction
Consultant WSP Canada Inc.
Memorial Bv - Portage Av/St Mary Av   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Early June 2019
Estimated to end Late October 2019
Approx. % completed Pre-Construction
Consultant WSP Canada Inc.
Memorial Bv - York Av/Broadway   View Map
Facility type Pedestrian / Cycling
Type of work New - Pedestrian / Cycling Construction
Estimated to start Early June 2019
Estimated to end Late October 2019
Approx. % completed Pre-Construction
Consultant WSP Canada Inc.
Memorial Bv - York Av/St Mary Av   View Map
Facility type Street
Type of work Reconstruction
Estimated to start Early June 2019
Estimated to end Late October 2019
Approx. % completed Pre-Construction
Consultant WSP Canada Inc.
Memorial Bv / 100m South of Portage Av   View Map
Facility type Signal
Type of work Signal Improvements
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Molson St - Nottingham Av/Union Av E   View Map
Facility type Street
Type of work Reconstruction
Estimated to start Summer 2018
Estimated to end Spring 2019
Approx. % completed 95
Consultant WSP Canada Inc.
Contractor Darco Enterprises Ltd.
Moray St - Saulteaux Cr/Moray St   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Summer 2018
Estimated to end Spring 2019
Approx. % completed 95
Consultant AECOM Canada Ltd
Contractor Nelson River Construction Inc.
Morpeth Bv - North End/Taylor Av   View Map
Facility type Sidewalk
Type of work New - Sidewalk Construction
Estimated to start Summer 2018
Estimated to end Spring 2019
Approx. % completed 95
Consultant AECOM Canada Ltd
Mountain Av - Arlington St/Airlies St   View Map
Facility type Sidewalk
Type of work Reconstruction
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Consultant City Of Winnipeg - Engineering Division
Mutchmor Cs- Tu Pelo Av/Tu Pelo Av   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Summer 2018
Estimated to end Spring 2019
Approx. % completed 95
Consultant WSP Canada Inc.
Contractor Darco Enterprises Ltd.
Nairn Av - Grey St/Panet Rd   View Map
Facility type Street
Type of work Preservation
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Nairn Av - Panet Rd/Grey St   View Map
Facility type Street
Type of work Preservation
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Ness Av - Olive St/Moray St   View Map
Facility type Street
Type of work Mill and Fill
Estimated to start Mid May 2019
Estimated to end Late June 2019
Approx. % completed 80
Consultant Stantec Consulting Ltd
Contractor Bituminex Paving Ltd
Notre Dame Av - Portage Av/Princess St   View Map
Facility type Street
Type of work Reconstruction
Estimated to start Summer 2018
Estimated to end Late August 2019
Approx. % completed 95
Consultant AECOM Canada Ltd
Contractor J.C. Paving Ltd.
Additional information Click here
Notre Dame Av/King Edward St   View Map
Facility type Signal
Type of work Signal Improvements
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Notre Dame Av/Weston St   View Map
Facility type Signal
Type of work Signal Improvements
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Partridge Av/Royal Av-Powers St/Andrews St   View Map
Facility type Alley
Type of work Reconstruction
Estimated to start Summer 2018
Estimated to end Spring 2019
Approx. % completed 95
Consultant WSP Canada Inc.
Contractor J.C. Paving Ltd
Pembina Hw - Grant Av/Osborne St   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Summer 2018
Estimated to end Spring 2019
Approx. % completed 95
Consultant WSP Canada Inc.
Contractor J.C. Paving Ltd.
Additional information Click here
Pembina Hw - Grant Av/Osborne St   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Summer 2018
Estimated to end Spring 2019
Approx. % completed 95
Consultant WSP Canada Inc.
Contractor J.C. Paving Ltd.
Additional information Click here
Pembina Hw - Minerva Av/St. Norbert Bridge   View Map
Facility type Street
Type of work Preservation
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Pembina Hw - Rapid Transit Corridor Underpass   View Map
Facility type Bridge
Type of work New - Rapid Transit Underpass Installation
Estimated to start Spring 2017
Estimated to end Spring 2020
Approx. % completed 30
Consultant Plenary Roads
Contractor PCL
Additional information Click here
Pembina Hw/Southpark Dr   View Map
Facility type Signal
Type of work New - Rapid Transit Signal Installation
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Contractor Black & McDonald Limited / Harris Holdings Ltd.
Peony Av - Verbena St/Viola St   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Summer 2018
Estimated to end Spring 2019
Approx. % completed 95
Consultant City Of Winnipeg - Engineering Division
Contractor Darco Enterprises Ltd.
Portage Av / Portage Av   View Map
Facility type Signal
Type of work Signal Improvements
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Portage Av / Ronald St   View Map
Facility type Signal
Type of work Signal Improvements
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Portage Av/Linwood St   View Map
Facility type Signal
Type of work Signal Improvements
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Preston Av/Westminster Av-Ethelbert St/Home St   View Map
Facility type Alley
Type of work Reconstruction
Estimated to start Summer 2018
Estimated to end Spring 2019
Approx. % completed 95
Consultant WSP Canada Inc.
Contractor J.C. Paving Ltd.
Princess St - Willaim Av/Donald St   View Map
Facility type Street
Type of work Mill and Fill
Estimated to start Summer 2018
Estimated to end Late August 2019
Approx. % completed 95
Consultant AECOM Canada Ltd
Contractor J.C. Paving Ltd.
Princess St - William Av/Notre Dame Av   View Map
Facility type Street
Type of work Mill and Fill
Estimated to start Summer 2018
Estimated to end Late August 2019
Approx. % completed 95
Consultant AECOM Canada Ltd
Contractor J.C. Paving Ltd.
Additional information Click here
Provencher Bv - Des Meurons St/Archibald St   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Mid May 2019
Estimated to end Late June 2019
Approx. % completed 95
Consultant Stantec Consulting Ltd.
Contractor Bituminex Paving Ltd
Rapid Transit Corridor - Phase 2   View Map
Facility type Rapid Transit Corridor
Type of work New - Rapid Transit Corridor
Estimated to start Summer 2016
Estimated to end Spring 2020
Approx. % completed 30
Consultant Plenary Roads
Contractor PCL
Additional information Click here
Regent Av W/Lagimodiere Bv   View Map
Facility type Signal
Type of work Signal Improvements
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Roberts Cr - Agnes Arnold Pl/Jefferson Av   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Summer 2018
Estimated to end Spring 2019
Approx. % completed 95
Consultant City Of Winnipeg - Engineering Division
Contractor Darco Enterprises Ltd.
Roblin Bv - Assiniboine Park Dr/Shaftesbury Bv   View Map
Facility type Street
Type of work Reconstruction
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Consultant City Of Winnipeg - Engineering Division
Roch St - Sydney Av/Trent Av   View Map
Facility type Sidewalk
Type of work Reconstruction
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Consultant City Of Winnipeg - Engineering Division
Salter St / Mountain Av   View Map
Facility type Signal
Type of work Signal Improvements
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Salter St / Selkirk Av   View Map
Facility type Signal
Type of work Signal Improvements
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Sara Av/Westminster Av-Langside St/Furby St   View Map
Facility type Alley
Type of work Reconstruction
Estimated to start Summer 2018
Estimated to end Spring 2019
Approx. % completed 95
Consultant WSP Canada Inc.
Contractor J.C. Paving Ltd
Sargent Av/Dominion St   View Map
Facility type Signal
Type of work Signal Improvements
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Sargent/Ellice Av-Arlington St/Alverstone St   View Map
Facility type Alley
Type of work Reconstruction
Estimated to start Summer 2018
Estimated to end Mid June 2019
Approx. % completed 95
Consultant WSP Canada Inc.
Contractor J.C. Paving Ltd.
Saskatchewan Av - 2450 Saskatchewan Av/Moray St   View Map
Facility type Street
Type of work Reconstruction
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Consultant AECOM Canada Ltd
Contractor Nelson River Construction Inc.
Saskatchewan Av - Moray St/Sturgeon Rd   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Consultant AECOM Canada Ltd
Contractor Nelson River Construction Inc.
Semple Av/Kilbride Av-Main St/Aikins St   View Map
Facility type Alley
Type of work Reconstruction
Estimated to start Summer 2018
Estimated to end Spring 2019
Approx. % completed 95
Consultant WSP Canada Inc.
Contractor J.C. Paving Ltd.
Sherbrook St - McDermot Av/Cumberland Av   View Map
Facility type Street
Type of work Mill and Fill
Estimated to start Summer 2018
Estimated to end Spring 2019
Approx. % completed 95
Consultant Stantec Consulting Ltd.
Contractor Darco Enterprises Ltd.
Sherbrook St / Westminster Av   View Map
Facility type Signal
Type of work Signal Improvements
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Speers Rd - Cottonwood Rd/Crestwood Cr   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Summer 2018
Estimated to end Spring 2019
Approx. % completed 95
Consultant AECOM Canada Ltd
Contractor J.C. Paving Ltd.
St James St - 190m North of Ellice Av/Sargent Av   View Map
Facility type Street
Type of work Reconstruction
Estimated to start Late July 2019
Estimated to end Mid October 2019
Approx. % completed Planned
Consultant Morrison Hershfield Limited
St James St/Sargent Av   View Map
Facility type Signal
Type of work Signal Improvements
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
St Mary Av - Vaughan St/Memorial Bv   View Map
Facility type Sidewalk
Type of work Reconstruction
Estimated to start Spring 2018
Estimated to end Summer 2019
Approx. % completed 0
Consultant City Of Winnipeg - Engineering Division
St Mary Av/Garry St   View Map
Facility type Signal
Type of work Signal Improvements
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
St Mary Av/Osborne St N/Memorial Bv   View Map
Facility type Signal
Type of work Signal Improvements
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
St Matthews Av/Valour Rd   View Map
Facility type Signal
Type of work Signal Improvements
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Stafford St - Corydon Av / McMillan Av   View Map
Facility type Sidewalk
Type of work Reconstruction
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Consultant City Of Winnipeg - Engineering Division
Stafford St - Yale Av / Corydon Av   View Map
Facility type Sidewalk
Type of work Reconstruction
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Consultant City Of Winnipeg - Engineering Division
Sun Valley Dr - Kingsdale Rd/Sunny Hills Rd   View Map
Facility type Sidewalk
Type of work Reconstruction
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Consultant City Of Winnipeg - Engineering Division
Swindon Wy - Portsmouth Bv/Park Bv E   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Summer 2018
Estimated to end Spring 2019
Approx. % completed 80
Consultant AECOM Canada Ltd
Contractor Darco Enterprises Ltd.
Taylor Av/Waverley St   View Map
Facility type Signal
Type of work Signal Improvements
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Thom Av E - Wabasha St/Day St   View Map
Facility type Sidewalk
Type of work Reconstruction
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Consultant City Of Winnipeg - Engineering Division
Thom Av W - Day St/Winona St   View Map
Facility type Sidewalk
Type of work Reconstruction
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Consultant City Of Winnipeg - Engineering Division
Troy Av - McPhillips St/Fife St   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Summer 2018
Estimated to end Spring 2019
Approx. % completed 95
Consultant City Of Winnipeg - Engineering Division
Contractor Darco Enterprises Ltd.
University Cr/Dafoe Rd   View Map
Facility type Signal
Type of work Signal Improvements
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Walmer St/Kirkdale St - Lawndale Av/Birchdale Av   View Map
Facility type Alley
Type of work Reconstruction
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Consultant WSP Canada Inc.
Waverley St - Grandmont Bv/City Limit   View Map
Facility type Street
Type of work Reconstruction
Estimated to start Summer 2019
Estimated to end Fall 2020
Approx. % completed Planned
Consultant Dillon Consulting Limited
Waverley St / Lindenwood Pl / Seel Av   View Map
Facility type Signal
Type of work Signal Improvements
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Waverley St/Hurst Wy/Wilkes Av   View Map
Facility type Signal
Type of work Signal Improvements
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
Waverley Underpass Project - Taylor Av / Waverley St / Wilkes Av / Grant Av   View Map
Facility type Bridge
Type of work New - Bridges Underpass Installation
Estimated to start Spring 2017
Estimated to end Fall 2019
Approx. % completed 10
Consultant Dillon Consulting Limited
Contractor Maple Leaf Construction Ltd.
Additional information Click here
Waverley Underpass Project - Taylor Av / Waverley St / Wilkes Av / Grant Av   View Map
Facility type Street
Type of work Bridge - Roadway Reconstruction
Estimated to start Spring 2017
Estimated to end Fall 2019
Approx. % completed 10
Consultant Dillon Consulting Limited
Contractor Maple Leaf Construction Ltd.
Additional information Click here
Wellington Av/Sargent Av-Banning St/Lipton St   View Map
Facility type Alley
Type of work Reconstruction
Estimated to start Summer 2018
Estimated to end Spring 2019
Approx. % completed 95
Consultant WSP Canada Inc.
Contractor J.C. Paving Ltd.
Wellington Av/Sargent Av-Toronto St/Beverley St   View Map
Facility type Alley
Type of work Reconstruction
Estimated to start Summer 2018
Estimated to end Spring 2019
Approx. % completed 95
Consultant WSP Canada Inc.
Contractor J.C. Paving Ltd
West Alexander Pedestrian and Cycling Corridor   View Map
Facility type Pedestrian / Cycling
Type of work New - Pedestrian / Cycling Construction
Estimated to start Summer 2017
Estimated to end Spring 2019
Approx. % completed 95
Consultant Stantec Consulting Ltd.
Contractor Darco Enterprises Ltd.
Additional information Click here
West Alexander Pedestrian and Cycling Corridor   View Map
Facility type Pedestrian / Cycling
Type of work New - Pedestrian / Cycling Construction
Estimated to start Summer 2018
Estimated to end Spring 2019
Approx. % completed 95
Consultant Stantec Consulting Ltd.
Contractor Darco Enterprises Ltd.
Additional information Click here
Westminster Av/Wolseley Av-Evanson St/Wolseley Av   View Map
Facility type Alley
Type of work Reconstruction
Estimated to start Summer 2018
Estimated to end Mid June 2019
Approx. % completed 95
Consultant WSP Canada Inc.
Contractor J.C. Paving Ltd.
Whitetail Dr- Chalfont Rd/Eldridge Av   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Summer 2018
Estimated to end Spring 2019
Approx. % completed 80
Consultant AECOM Canada Ltd
Contractor Darco Enterprises Ltd.
Whitley Dr- Ashworth St/Hawkins Cr   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Summer 2018
Estimated to end Spring 2019
Approx. % completed 95
Consultant WSP Canada Inc.
Contractor J.C. Paving Ltd.
Woodstock Ln- North End/Eldridge Av   View Map
Facility type Street
Type of work Rehabilitation
Estimated to start Summer 2018
Estimated to end Spring 2019
Approx. % completed 80
Consultant AECOM Canada Ltd
Contractor Darco Enterprises Ltd.
Yarwood Av/Wellington Av-Ingersoll St/Sherburn St   View Map
Facility type Alley
Type of work Reconstruction
Estimated to start Summer 2018
Estimated to end Spring 2019
Approx. % completed 95
Consultant WSP Canada Inc.
Contractor J.C. Paving Ltd.
York Av - Memorial Bv / Osborne St N   View Map
Facility type Street
Type of work Reconstruction
Estimated to start Early June 2019
Estimated to end Late October 2019
Approx. % completed Pre-Construction
Consultant WSP Canada Inc.
York Av/Garry St   View Map
Facility type Signal
Type of work Signal Improvements
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned
York Av/Memorial Bv   View Map
Facility type Signal
Type of work Signal Improvements
Estimated to start To Be Determined
Estimated to end To Be Determined
Approx. % completed Planned

Disclaimer and Indemnity:

The information on this web site is provided as a public service and should be used for general information purposes only. Although the information provided represents the planned capital work on city infrastructure for the current year, the City of Winnipeg cannot guarantee that it is accurate or current at all times. Although it is rare that projects are not finished within the stated timeframe, the City cannot guarantee that the work will be completed in all cases.

The information on this web site is subject to change without notice. Winnipeg.ca AND ITS AFFILIATES ARE NOT RESPONSIBLE IN ANY MANNER FOR DIRECT, INDIRECT, SPECIAL OR CONSEQUENTIAL DAMAGES HOWSOEVER CAUSED RESULTING FROM THE USE, MISUSE OR MISINTERPRETATION OF ANY CONTENT, PRODUCTS OR SERVICES PROVIDED BY THIS WEB SITE.

By using this site, you agree to indemnify, defend and hold harmless City of Winnipeg and its officials, officers, employees and authorized representatives from and against any liability, loss injury (including injuries resulting in death), demand, action, cost, expense, or claim of any kind, including but not limited to lawyer's fees, relating in any way to your use of the contents, or services provided by this web site.