Last Update: January 22, 2019 12:00 AM

Updated 11 Jan 2019 10:28 AM
Academy Rd Westbound
Queenston St to Brock St
Expected Duration: 17 Sep 2018 - 31 Jan 2019
WB curb lane closed for building construction.

 
Carlton St Southbound
Ellice Av to Graham Av
Expected Duration: 22 Jan 2019 03:00 AM - 23 Jan 2019 03:00 AM
East curb lane closed for special event parking.

Updated 23 Jul 2018 03:00 PM
Carlton St Southbound
Graham Av to St Mary Av
Expected Duration: 09 Jul 2018 - 03 Oct 2021
West curb lane closed for building construction.

Updated 07 Nov 2018 12:52 PM
Carlton St Southbound
Graham to St. Mary
Expected Duration: 21 Jun 2016 - 30 Apr 2019
Carlton will be reduced to one lane due to building construction.

 
Carlton St Southbound
York Av to Broadway Af
Expected Duration: 01 Feb 2019 08:00 AM - 01 Feb 2019 05:30 PM
West curb lane closed for special event parking.

 
Corydon Av Eastbound
Montrose St to Waverley St
Expected Duration: 21 Jan 2019 09:00 AM - 22 Jan 2019 03:00 PM
EB curb lane closed for hydro work from 9-3 daily.

 
Corydon Av Eastbound
Oxford St to Cambridge St
Expected Duration: 22 Jan 2019 09:00 AM - 23 Jan 2019 03:00 PM
EB curb lane closed from 9-3 daily for hydro work.

 
Cumberland Av Eastbound
Langside St to Balmoral St
Expected Duration: 15 Jan 2019 - 25 Jan 2019 03:00 PM
South curb lane closed for electrical work from 9-3 daily.

Updated 18 Jan 2019 11:14 AM
Des Meurons St Northbound
Deschambault St to Provencher Bv
Expected Duration: 17 Jan 2019 09:00 AM - 22 Jan 2019 03:00 PM
NB curb lane closed for street light repairs from 9-3 daily.

Updated 04 Jan 2019 01:36 PM
Empress St Northbound
75m S of Jack Blick Av to St Matthews Av
Expected Duration: 02 Jan 2019 - 28 Feb 2019
NB curb lane closed for construction.

 
Fort St Northbound
Graham Av to Portage Av
Expected Duration: 05 Dec 2018 - 05 May 2019
Fort will be reduced to one lane for through traffic due to building construction.

 
Garry St Southbound
Portage Av to Graham Av
Expected Duration: 07 Jan 2019 - 08 Feb 2019
East curb and 2nd lane closed for hydro work.

Updated 10 Jul 2018 08:06 AM
Graham Av Eastbound & Westbound
Main St to Fort St
Expected Duration: 16 Jul 2018 - 15 Jul 2020
Graham will be closed to all traffic except buses due to building construction.

 
Hargrave St Northbound
St Mary Av to Graham Av
Expected Duration: 22 Jan 2019 03:00 AM - 23 Jan 2019 03:00 AM
East curb lane closed for special event parking.

 
Main St Southbound
Fernbank Av to Red River Bv
Expected Duration: 22 Jan 2019 09:00 AM - 23 Jan 2019 03:00 PM
SB curb lane closed for streetlight repair from 9-3 daily.

 
Main St Northbound
Fort Gibraltar Tl to Forks Market Rd
Expected Duration: 04 Feb 2019 - 06 Feb 2019
NB curb lane closed for festive lighting removals from 9-3 daily.

Updated 07 Jan 2019 11:29 AM
Main St Southbound
Portage Av to Graham Av
Expected Duration: 01 Oct 2018 06:00 PM - 28 Feb 2019 07:00 AM
SB curb lane closed for construction in the evenings.

Updated 15 Jan 2019 10:43 AM
Main St Southbound
Portage Av to Graham Av
Expected Duration: 04 Jan 2019 07:00 PM - 04 Mar 2019 05:00 AM
SB curb and 2nd lane closed on weekends only for building construction.

Updated 17 Jan 2019 02:33 PM
Main St Southbound
Templeton Av to Partridge Av
Expected Duration: 16 Jan 2019 09:00 AM - 30 Jan 2019 03:00 PM
SB curb lane closed for street light repairs.

 
Main St Southbound
York Av to Broadway Af
Expected Duration: 23 Jan 2019 09:00 AM - 25 Jan 2019 03:00 PM
SB curb lane closed for moving trucks from 9-3 daily.

 
Maryland Bridge Northbound & Southbound
Cornish Av to Academy Rd
Expected Duration: 24 Jan 2019 09:00 AM - 24 Jan 2019 03:00 PM
Median lanes closed for bridge work from 9-3.

 
McPhillips St Northbound & Southbound
Mapleglen Dr to Dafoe Bv
Expected Duration: 17 Jan 2019 09:00 AM - 25 Jan 2019 03:00 PM
Curb lanes closed for communications work from 9-3 daily.

 
Osborne St N Southbound
Broadway Af to Granite Wy
Expected Duration: 21 Jan 2019 - 04 Feb 2019
SB median lane closed for sewer work. Also the East side sidewalk over the bridge will be closed.

Updated 18 Jan 2019 12:45 PM
Pandora Av E Eastbound
Kanata St to Wabasha St
Expected Duration: 04 Feb 2019 - 08 Feb 2019
EB Pandora will be completely closed to all traffic due to sewer repairs. WB will be maintained.

Updated 11 Jan 2019 05:19 PM
Pembina Hw Southbound
Harrow St E to Jubilee Av
Expected Duration: 21 Dec 2018 - 21 Jan 2019
SB curb lane closed for road work.

Updated 13 Dec 2018 08:04 AM
Portage Av Westbound
Strathcona St to Empress St
Expected Duration: 12 Dec 2018 07:00 AM - 28 Feb 2019 05:00 PM
WB curb lane closed for construction through the underpass.

Updated 11 Jan 2019 01:07 PM
Provencher Bv Eastbound
St Jean Baptiste St to Des Meurons
Expected Duration: 17 Jan 2019 09:00 AM - 28 Jan 2019 03:00 PM
Single lane closed for communications work from 9-3 daily.

Updated 21 Jan 2019 12:45 PM
Regent Av W Eastbound & Westbound
Madeline St to Hoka St
Expected Duration: 15 Jan 2019 09:00 AM - 23 Jan 2019 03:00 PM
WB curb and EB middle lanes closed for sewer work from 9-3 daily.

Updated 16 Jan 2019 01:50 PM
River Av Westbound
Nassau St N to Wilmot Pl
Expected Duration: 06 Jun 2018 - 15 Feb 2019
South curb lane closed for construction.

 
Sargent Av Westbound
Balmoral St to Sherbrook St
Expected Duration: 24 Jan 2019 09:00 AM - 28 Feb 2019 03:00 PM
WB curb lane closed for hydro work from 9-3 daily.

Updated 02 Jan 2019 08:17 AM
Sherbrook St Northbound
Broadway Af to Portage Av
Expected Duration: 09 Oct 2017 - 31 Jan 2019
NB curb lane and bike lane closed for building construction.

 
St Mary Av Westbound
Carlton St to Edmonton St
Expected Duration: 09 Jul 2018 - 01 May 2022
North curb lane closed for building construction.

 
St Mary Av Westbound
Colony St to Good St
Expected Duration: 01 Feb 2019 - 31 Jul 2019
WB curb lane closed for building construction.

Updated 21 Dec 2018 08:22 AM
St Mary Av Westbound
Memorial Bv to Colony St
Expected Duration: 16 Jul 2018 - 31 Oct 2019
North curb lane closed for building construction.

 
St Vital Bridge Northbound & Southbound
Osborne St to Dunkirk Dr
Expected Duration: 22 Jan 2019 09:00 AM - 22 Jan 2019 03:00 PM
Curb lanes closed for bridge work from 9-3.

 
Tuxedo Av Westbound
Edgeland Bv to Chataway Bv
Expected Duration: 28 Jan 2019 09:00 AM - 04 Feb 2019 03:00 PM
WB curb lane closed for sewer work from 9-3 daily.

 
University Cr Southbound
Pembina Hw to Chancellor Matheson Rd
Expected Duration: 30 Jan 2019 09:00 AM - 01 Feb 2019 03:00 PM
SB curb lane closed for gas work from 9-3 daily.

 
Wilkes Av Westbound
Elmhurst Rd to Liberty St
Expected Duration: 17 Jan 2019 09:00 AM - 18 Jan 2019 03:00 PM
WB lane closed for hydro work. Traffic will be controlled by flagpersons from 9-3 daily.

Updated 16 Jan 2019 02:52 PM
York Av Eastbound
Carlton St to Hargrave St
Expected Duration: 22 Jan 2019 09:00 AM - 22 Jan 2019 03:00 PM
North curb and adjacent lane closed for crane work from 9-3 daily.